Dáil Éireann debate -
Wednesday, 15 Apr 1959

Vol. 174 No. 3

Ceisteanna—Questions. Oral Answers. - Sod-Turf Power Stations.

6.

asked the Minister for Industry and Commerce when and where each of the sod-turf power stations was commenced and completed; what each power station cost; and for how many months in each year since completion each of these stations has been in operation.

The information sought has been obtained from the Electricity Supply Board and is set out in the form of a tabular statement which, with the permission of the Ceann Comhairle, I propose to have circulated with the official report.

Following is the statement:—

Station

Commenced

Completed

Cost(£ million)

Portarlington

1946

January, 1950

1.5

Allenwood

1949

January, 1952

2.5

Miltown-Malbay

1954

November, 1956

0.32

Screeb

1954

August, 1957

0.36

Cahirciveen

1954

October, 1957

0.37

Gweedore

1955

March, 1958

0.37

Lanesborough

1955

September, 1958

0.91

RUNNING TIMES:

Portarlington, Allenwood and Lanesborough have been in continuous operation since completion. The months of running of each of the four small hand-won turf stations in each year since completion are shown below:

Months running

1956

1957

1958

1959

Miltown-Malbay

1

11

8

Nil

Screeb

4

8

Nil

Cahirciveen

2

7

2

Gweedore

4

3