Ceisteanna—Questions. Oral Answers. - Fostaíocht sa Ghaeltacht.

20. D'fhiafraigh

d'Aire na Gaeltachta an bhfuil aon dealramh air go mbeidh breis fostaíochta ar fáil sa Ghaeltacht i rith 1977; agus má tá, cá mbeidh sí.

Is cinnte go mbeidh breis fostaíochta ar fáil ar fud na Gaeltachta i rith na bliana 1977: meastar go gcruthófar suas le 1,000 post i mbliana. Foilsíodh clár togála monarchan le déanaí agus, le cead an Cheann Comhairle, cuirfear mór thimpeall sa Tuairisc Oifigiúil é.

Seo a leanas an clár:

GAELTARRA ÉIREANN

FACTORY BUILDING PROGRAMME 1977

SCHEDULE 1—ADVANCE FACTORIES

County

Location

Area sq. ft.

Completion Date

Total Cost

Expenditure 1977

Expenditure 1978

Expenditure Prior 1977

£

£

£

£

County Donegal

Fanad

2,000

August 1977

16,800

16,800

Gortahork

7,200

December 1977

95,000

65,000

30,000

Bunbeg

29,600

November 1977

325,000

240,000

85,000

Fintown

7,200

Finished

80,000

40,000

40,000

Ardara

7,200

February 1978

95,000

70,000

25,000

Totals: County Donegal

53,200

611,800

431,800

140,000

40,000

County Mayo

Bunacurry (Achill)

7,200

January 1978

95,000

70,000

25,000

Carratigue

7,200

December 1977

100,000

100,000

Belmullet

21,300

June 1978

245,000

95,000

150,000

Totals: County Mayo

35,700

440,000

265,000

175,000

County Galway

Tír an Fhia

7,200

December 1977

90,000

75,000

15,000

Carna

7,200

June 1978

93,000

50,000

43,000

Costello

22,000

December 1977

240,000

160,000

80,000

County Galway (ar lean)

Rosmuc Inis Mór

7,2002,000

May 1978August 1978

100,000 40,000

60,00030,000

40,00010,000

——

Inis Oirr

2,000

August 1978

40,000

30,000

10,000

Totals: County Galway

47,600

603,000

405,000

198,000

County Cork

Cuill Aodha

2,000

November 1977

20,000

17,000

3,000

Grand Totals—

Advance Factories 15

138,500

1,674,800

1,118,800

516,000

40,000

GAELTARRA ÉIREANN

FACTORY BUILDING PROGRAMME 1977

SCHEDULE 2—CONSTRUCTION FOR APPROVED PROJECTS

County

Location

Area sq. ft.

Completion Date

Total Cost

Expenditure 1977

Expenditure 1978

Expenditure Prior 1977

£

£

£

£

County Donegal

Bunbeg

6,500

August 1977

72,000

72,000

Annagary

12,430

July 1977

65,000

65,000

Dungloe

21,500

Complete

207,000

22,000

185,000

Kilcar

80,740

June 1978

987,500

510,000

152,500

325,000

Kilcar

Services

September, 1977

60,000

20,000

40,000

Totals: County Donegal

121,170

1,391,500

689,000

192,500

510,000

County Mayo

Carratigue

Renovation

May 1977

20,000

20,000

Tourmakeedy

560

September 1977

12,000

11,000

1,000

Totals: County Mayo

560

32,000

31,000

1,000

County Galway

Rossaveal

6,500

Complete

125,000

35,000

90,000

Rosmuc

12,000

June 1978

148,500

48,500

100,000

County Galway (ar lean)

Inverin

12,200

October 1977

145,000

100,000

35,000

10,000

Carraroe

33,550

December 1977

388,000

213,000

175,000

Spiddal

53,300

June 1977

399,000

248,000

49,000

102,000

Carna

Renovation

August 1977

30,000

30,000

Carna

4,000

September 1977

48,000

48,000

Inis Meáin

2,100

December 1977

40,000

40,000

Totals: County Galway

123,650

1,323,500

762,500

359,000

202,000

County Cork

Ballymakeera

9,500

October 1977

120,000

120,000

County Waterford

Ring

2,800

December 1977

20,000

29,000

County Meath

Gibbstown

13,500

May 1977

95,000

20,000

75,000

Rathcairn

29,000

November 1977

322,000

122,000

200,000

Totals: County Meath

42,500

417,000

142,000

275,000

Grand Totals—

Project Factories 18

300,180

3,304,000

1,764,500

552,500

987,000

GAELTARRA ÉIREANN

BUILDING PROGRAMME 1977

SCHEDULE 5—DEVELOPMENT AND SERVICES FOR INDUSTRIAL ESTATES

County

Total Cost

Expenditure 1977

Expenditure 1978

£

£

£

County Donegal

380,000

260,000

120,000

County Mayo

220,000

80,000

140,000

County Galway

350,000

250,000

100,000

County Cork

80,000

10,000

70,000

Totals

1,030,000

600,000

430,000

Tuigfidh an tAire nach dtarlóidh na postanna seo de bhrí go bhfuil an tAire ag trácht orthu. An féidir leis a rá liomsa cén cruthú atá ann go mbeidh 1,000 ann i mbliana?

Bíonn on-going work ar siúl i gcónaí. Ón am a thosnaíonn Gaeltarra ag lorg suíomh do mhonarcha go dtí go ndéantar forbairt ar an suíomh agus go gcuirtear na h-áiseanna go léir isteach ann, tógann an obair sin go léir cúpla bliain. Cuir i gcás b'fhéidir dhá bhliain ó shin go bhfuair Gaeltarra suíomh do mhonarcha, gur déanadh forbairt uirthi agus anois tá tionscal ar siúl sa bhfoirgneamh sin. Tá sceideal iomlán agam anseo a bhaineann le clár tógála Ghaeltarra Éireann do 1977 agus 1978, an t-am a críochnóidh an obair sin, an méad airgid agus gach rud mar sin a bhaineann le gach ceantar Ghaeltachta. Mar eolas don Teachta, tá 18 monarchana á dtógáil do thógraí atá ceadaithe. Tá 15 réamh-mhonarchana á dtógáil.

Tá neart páipéarachais agus figúirí ann, ach an cruthú is fearr atá againn ná nár chruthaíodh ach breis agus 500 post anuraidh. Tá an tAire ag rá go dtarlóidh sé sin i mbliana agus ag iarraidh orainn é sin a ghlacadh gan chruthúnas ceart a bheith ann.

Caithimid smaoin— eamh ar an dul chun cinn atá déanta ag Gaeltarra Éireann le ceithre bliain anuas nuair a bhí deacrachtaí mór an domhain ag cur isteach orthu agus nuair a cuireadh 500 post ar fáil ar meán gach bliain i rith na tréimhse sin. Tá sé sin ar fheabhas ar fad. Anois nuair atá cúrsaí eacnamaíochta ag dul ar aghaidh——

Níl siad ag dul ar aghaidh.

Tá an bun-structúr ann agus tá mé cinnte——

De bhrí go bhfuil toghachán ag teacht——

Ní ceart don Teachta bheith ag cur isteach. Tá mé ag dul ar aghaidh go ceist eile.

Top