Written Answers. - Athlone Government Offices.

410.

asked the Minister for Finance if he will state in relation to the Government offices at Pearse Street, Athlone: (a) the cost of the acquisition of the site; (b) the cost of clearing the site; and (c) the cost of building, equipment and furnishing the new office.

(a) It is not customary to release details of the cost of site acquisition as this is considered to be a matter of confidentiality between the vendor and purchaser.

(b) Site clearance was carried out as part of the building contract at a cost of approximately £8,000.

(c) The final cost of the project has not yet been settled but it is expected to be in the region of £1.5 million. This figure includes demolition and building works, furniture and consultants fees.