asked the Minister for Agriculture if he considers that simplification of procedures governing the implementations of the farm building scheme under the Western Package would improve farmer response and increase uptake under the scheme; and the number and location of the completed schemes to date.
Written Answers. - Western Package.
806.
The programme under which EC Regulation 1820-80 (Western Package) operates is due for review in conjunction with the Commission in 1985 and consideration will be given to any changes considered necessary to render the package, including the on-farm element, more effective.
The position regarding projects completed at 30 September 1984 under the scheme for Orientation of Agricultural Production was as follows:
County |
Number |
Cavan |
4 |
Clare |
16 |
Cork |
2 |
Donegal |
2 |
Galway |
62 |
Kerry |
14 |
Leitrim |
1 |
Limerick |
— |
Longford |
8 |
Mayo |
11 |
Monaghan |
31 |
Roscommon |
98 |
Sligo |
26 |
Total |
275 |