Due to difficulties outside the Department's control progress on submission of the preliminary tender report has been slow due to difficulties which arose in determining the capacity of the lowest tender for the main contract to undertake the project. This necessitated considerable exploring by the design team in order to ascertain whether the lowest tender could secure a guarantee of a bond. In the event, the company were unable to secure a bond and they subsequently withdrew from the project.
On 9 October 1991 the Department conveyed approval to the design team to proceed to an examination of the next lowest tender. My Department are now awaiting the design team's report and recommendations.