100 Mr. E. Kenny asked the Minister for Health the extent, nature and date of placing of each capital contract in respect of hospital development in each health board area for the past three years; and if he will make a statement on the matter.

The significant hospital developments, that is those costing £500,000 or more in respect of which contracts were placed in the past three years, which were funded under my Department's Capital programme are as follows:

Project

Approved tender amount

Date of approval by Department to tender

1991

1992

1993

£

Dublin:

St. James's Hospital

—Cook Chill Kitchen

534,517.00

08.04.91

Beaumont Hospital

—Provision of MRI Equipment

1,819,191.00

23.12.91

Mater Misericordiae Hospital

—Laboratory/Psychiatic Development

1,495,266.00

28.02.92

Rotunda Hospital Dublin

—New Three Storey Block Development Suite and Theatres

1,557,494.75

19.09.91

St. Vincent's Hospital, Fairview

—New 40 bed acute unit

1,331,526.23

11.06.92

General Hospital, Tullamore

—Two New Operating Theatres

759,122.73

28.05.93

Mullingar General Hospital

—Phase 2A Development (Radiology, A & E, Out-Patients Department, Wards, Concourse and Theatres)

5,097,939.00

14.05.93

St. Luke's Hospital, Kilkenny

—First Phase Development: Three New Theatres, Maternity Delivery Suite, Paediatric Unit, I.C.U., C.S.S.D.

3,378,767.68

27.01.92

Waterford Regional Hospital

—Acute Psychiatric Unit

1,875,944.26

05.05.93

—Extension to Out-Patients Department

786,979.44

26.05.93

—Renal Dialysis/Medical Diagnostic Unit

717,925.74

28.09.93

Cork Regional Hospital

—Extensions and Alterations to I.C.U. and Cardiac Theatre

1,293,472.05

13.09.93

St. Mary's Orthopaedic Hospital, Cork

—Upgrading of Operating Theatres

972,603.58

13.09.93