Written Answers. - Kildare Group Water Schemes.

Charlie McCreevy

Question:

172 Mr. McCreevy asked the Minister for the Environment the number of group water schemes and regional water schemes under consideration and in progress in County Kildare; the purpose of each scheme; the actual and estimated costs of each scheme; and the expected competition date of each scheme. [3615/96]

The information requested is as follows:

Major Schemes

There are no regional water schemes at present under construction by, or on behalf of, Kildare County Council. My Department is funding a major refurbishment of the Leixlip water plant which has enabled Fingal County Council to make additional water available to Kildare County Council.

I have recently approved the appointment of consultants to prepare a preliminary report for the North-East Kildare water scheme. The cost of this scheme has not yet been authoritatively estimated.

Proposals for the following schemes have been submitted to my Department:

Scheme

Purpose

Estimated Cost

£

Castledermot Regional Water supply

To replace existing overloaded treatment plant

1,350,000

South Kildare Regional Water Supply

Laying of trunk main to serve the South Kildare area

2,800,000

Athy Water Supply

To improve the water supply to Athy town and surrounding area

1,540,000

Monasterevan Water Supply

To improve the water supply to Monasterevan

1,200,000

Alternative Water Supply Source for County Kildare

To identify possible alternative sources to supplement existing sources of supply

No estimate available

It is not possible to say when these schemes will reach construction stage.
Group Schemes
There are 5 group water schemes in progress, as follows:

Scheme

Purpose

Estimated Cost

£

Castlewarden

To serve 6 houses

11,710

Coolcarrigan

To serve 22 houses and 2 farms

40,280

Tinnycross/Breincan

To serve 5 houses and 1 farm

13,224

Mylerstown

To serve 3 houses and 1 farm

7,088

Smithstown-Clonaugh

To serve 4 houses and 2 farms

5,798

A further 25 group schemes are at various stages of planning. The information requested on these schemes is being compilted and will be forwarded to the Deputy as soon as possible.