I understand from the Office of Public Works, which is acting as my Department's agent in this matter, that as of 4 April 2001 the following progress had been made towards reinstating the site: field containing two basement areas – 95% complete; main car park, same side of road – 60% complete; service road – 30% complete; removal of main sewage works – 100% complete; reinstatement of road boundary between the main entrance and the junction of the Green Road and the Crag Road – 95% complete; telecom ducts and ESB cables have been removed from the site to the junction of the Crag Road and the Green Road; overflow car park – 20% complete; equipment building – 100% complete; and sewage treatment polishing system – 10% complete.