149 Mr. Ring asked the Minister for Justice, Equality and Law Reform if he will provide a list of consultants who have been employed by his Department from June 1997 to date; and the fees which have been paid to each such consultant. [22543/01]

I wish to refer the Deputy to previous parliamentary questions on consultants engaged by my Department – Parliamentary Questions Nos. 377 on 26 June 2001 and 206 on 11 April 2001. The changes which have occurred since then are as set out in the following tabular statement.

To facilitate the prisons building and refurbishment programme, my Department has, on an ongoing basis, engaged consulting architects, consulting engineers and other specialists as appropriate to each particular project. The total cost for these services to my Department over the period specified is estimated at £4.5 million approximately. It would not, however, be appropriate to break these figures down to reveal the cost of each consultancy or contract because of the market sensitive nature of this information. Furthermore, in the interest of the security of prisons, it is not considered appropriate to identify consultancy firms or individual consultants in relation to prison works or prison building projects.

Name of Consultancy Firm

Nature of Work/Study

Total CostIR£

Generation Graphics

Design logo for Prisons Probation Service

4,700

Edelman PR

To develop and implement a public relations strategy for the formal launch of the National Anti-Racism Awareness Programme

Nil paid to date

Browne Atlantic Ltd

To review existing research to ascertain the information already available on the attitudes and opinions among the general public and all key audiences on racism and minority ethnic groups and to specify what further information is needed as baseline research for National Anti-Racism Awareness Programme

6,933.96

Name of Consultancy Firm

Nature of Work/Study

Total CostIR£

Public Communications Centre

To design logo to develop a corporate brand image/identity for the National Anti-Racism Awareness Programme

Nil paid to date

RES Consulting

IT Network Support Skills, for Prison Service Systems

214,822.86

Terry Lawlor, Consultant

DataEase Consultancy, for Prison Service Systems and Departmental Systems

18,321.82

International Computers Ltd (Head of consortium of various companies following EU procurement)

Supply of IT consultancy services and systems in relation to the Prison Service

180,622.72

G. Gardner, Consultant

Examination of provision for electronic fingerprint system for Asylum Seekers

Nil paid to date

PriceWaterhouseCoopers (Head of consortium of various companies following EU procurement) Lotus, EPS, CARA, Unipower

Supply of IT consultancy services and systems for Department(Mid 1998 for 3 years approx.)Supply of IT consultancy services and systems to the Department (2001)

201,773.42

Gartner Group

Subscription Service for access to IT Advise Database and commissioning of specific information requests regarding Strategic Information Technology directions and forecasts

6,840.00

Dr. Yvonne Galligan

Engaged as a rapporteur for a Non-Government Organisations Forum held in Dublin Castle on 10 May 2000 to report on proceedings

995.14

Genesis Europe

Assisting the Department in the design and implementation of a consultation process to develop the National Plan for Women, 2001-2006

16,576.67

Martin Turner

Commissioned to produce five cartoons on gender equality, to be used on the NDP Gender Equality Unit website and factsheets to be published, which outlined gender equalities in five different areas (transport, housing, rural development/agriculture, education/training and industrial development)

500

University of Stathclyde

Providing training on gender equality issues to policy makers in Government departments and agencies, which is part of the remit of the Equality Division

28,221.30

WRC, Social and Economic

Advice on project selection, project management and project strand support for Equality for Women Measures of the Regional Operational Programmes of the National Development Plan 2000 – 2006

251,012

Centre for Social and Educational Research

To develop comprehensive guidelines for the establishment, operation, management and administration of Garda Youth Diversion Projects

13,783.50

Cyril Connolly, Consultant Statistician

To examine the production and presentation of statistics in the Office of the Refugee Applications Commission

Nil paid to date

Hay Management Consultants

Performance Management and Development (ongoing)

73,781 (to date)

Centre for Social and Educational Research

Participants in Garda Youth Diversion Projects

22,275 (to date)

F. LundstromResearch Consultant

Development of Delivery Systems for new Sex Offenders Treatment Programme

46,529 (to date)

MORI Marketing Research Consultant

Review of Parental Leave Act, 1988

29,775.98 (to date)

Newmarket Consulting

Attitudinal Research in relation to Parental Leave

31,920.00

Tom Martin & Associates

A Review of Equality Initiatives within The Justice and Equality Sector

10,059.60

Kelleher Associates

Current and Future Needs and Responses to Women who Experience Violence

19,000

Mr. Brendan O'Friel

Strategic Effectiveness Programme (STEP)

1,000 stg

KPMG

Consultancy in connection with the National Disability Authority

22,316.02

Paul Francis

Design work on two leaflets for the NDA

1,188.00

Paul Francis

Design work for a leaflet and poster for the Public Service careers expo 2001

1,600.80

Paul Francis

Design Art Work for National Information Day on Disability, 2001

Nil paid to date

PriceWaterhouseCooper

Carryout a value for money audit on a company “Vantastic Dial a Ride”

Nil paid to date

Corporate Events

Organise and manage Irish National Information Day for people with disabilities

Nil paid to date

La Touche Bond Solon

Provide training for local management in Civil Litigation Claims management

11,155.50

Deloitte and Touche

Carry out Phase 3 of a review of structures and operating systems within the Garda Síochána

285,866.94

Irish Management Institute

Designing a Performance Management System for the Garda Síochána

18,000

International Computers Ltd

To assist with the implementation of a new financial management system for the Irish Prison Service

127,379.99

Name of Consultancy Firm

Nature of Work/Study

Total CostIR£

Helm Corporation

Assist with the evaluation of tenders in respect of the supply and implementation of the new Financial Management System for the Irish Court Service, An Garda Síochána and the Department of Justice, Equality and Law Reform

Nil paid to date

Oracle

To complete the file server side design for the Oracle services in the context of the role out of Oracle Financials to the Irish Prison Service

Nil paid to date

Prospectus Business Consultants

To provide Consultancy Services in the development of business plans for prisons

4,836.00

IBM

To complete set up at the operating system level of both the Oracle Financial application and development

Nil paid to date