Written Answers - Swimming Pool Projects.

David Stanton

Question:

127 Mr. Stanton asked the Minister for Arts, Sport and Tourism the amount grant aided by his Department to enable the refurbishment or construction of swimming pools in 2002; the locations of the pools in question; the amount that he has or will have to spend in 2003; the number of applications for grant aid before his Department; the status of each application; the further action needed in order for each application to be processed further; and if he will make a statement on the matter. [5704/03]

Under the local authority swimming pool programme, which is administered by my Department, the amount grant aided in 2002 to enable the refurbishment or construction of swimming pools was just under €3.9 million. Swimming pool projects in Ennis, Monaghan, Roscommon, Wicklow, Ballinasloe and Finglas received grant-aid last year. The Estimates provision for the swimming pool programme for 2003 is €9 million.

Under the swimming pool programme, there are four stages in a swimming pool project following the submission of a feasibility study. These, in order of progress, are: preliminary report; contract documents; tender and construction. My Department's technical advisers, the Office of Public Works, Office of Public Works, evaluate each stage and local authorities cannot proceed to the next stage of a project unless prior approval issues from my Department. Grant-aid is allocated only when tenders have been approved for the project and will be capped at the time of allocation.

There are 43 applications in-hand in the swimming pool programme and these are at various stages of progress. The current status of these applications is set out in the form of a tabular statement which I propose to circulate in the Official Report.

Status of Swimming Pool Applications

Name of Pool

Current Status

Ferrybank, Wexford

Feasibility Study received

Greystones

Feasibility Study received

Buncrana

Feasibility Study received

Ballaghadreen

Feasibility Study received

Bray

Feasibility Study received

Birr

Feasibility Study received

Monaghan

Feasibility Study received

Roscrea

Approval to appoint consultants for Preliminary Report

Loughrea

Approval to appoint consultants for Preliminary Report

Ballybofey/Stranorlar

Approval to appoint consultants for Preliminary Report

New Ross

Approval to appoint consultants for Preliminary Report

Castlebar

Awaiting Preliminary Report

Edenderry

Preliminary Report received

Clara

Preliminary Report received

Ballymun

Preliminary Report received

Letterkenny

Preliminary Report received

Claremorris

Preliminary Report received

Dundrum

Preliminary Report received

Ballybunion

Preliminary Report received

Drogheda

Addendum to Preliminary Report received

Ballyfermot

Preliminary Report approved

Name of Pool

Current Status

Glenalbyn

Preliminary Report approved

Skerries

Preliminary Report approved

Athy

Preliminary Report approved

Portlaoise

Preliminary Report approved

Grove Island

Preliminary Report approved

Clondalkin

Preliminary Report approved

Jobstown

Preliminary Report approved

Thurles

Preliminary Report approved

Tullamore

Preliminary Report approved

Killarney

Preliminary Report approved

Askeaton

Preliminary Report approved

Kilkenny

Preliminary Report approved

Longford

Approval to appoint Design team for Contract Documents

Naas

Contract Documents received

Youghal

Contract Documents received

Portarlington

Contract Documents received

Dunmanway

Contract Documents received

Tuam

Contract Documents received

Clonmel

Contract Documents approved

Churchfield, Cork

Contract Documents approved

Tralee, Clounalour

Tenders received

Cobh

Tenders received

Question No. 128 answered with Question No. 116.
Question No. 129 answered with Question No. 113.