SWS Post-Primary 2010
COUNTY / SCHOOL
|
PROJECT APPLICATION
|
TOTAL PAID
|
CARLOW
|
|
|
ST MARYS ACADEMY, STATION ROAD
|
OTHER STRUCTURAL IMPROVEMENTS
|
235,352.50
|
COLAISTE MHUIRE CARLOW, KNOCKBEG
|
TOILET FACILITIES
|
104,953.00
|
PRESENTATION COLLEGE, ASKEA
|
ROOF WORKS
|
215,447.46
|
PRESENTATION/DE LA SALLE CARLOW, MHUINE BHEAG
|
ROOF WORKS
|
395,360.00
|
CARLOW VOCATIONAL SCHOOL, KILKENNY ROAD, CARLOW
|
TOILET FACILITIES
|
77,555.46
|
VOCATIONAL SCHOOL MUINEBEAG
|
WINDOW PROJECTS
|
50,568.73
|
TOTAL CARLOW
|
|
1,079,237.15
|
CAVAN
|
|
|
ST CLARES COLLEGE, BALLYJAMESDUFF
|
ELECTRICAL WORKS
|
250,918.85
|
ROYAL SCHOOL CAVAN
|
ROOF WORKS
|
52,250.00
|
ST BRICKINS BELTURBET
|
EXTERNAL ENVIRONMENT PROJECTS
|
22,000.00
|
VIRGINIA VOCATIONAL SCHOOL
|
OTHER STRUCTURAL IMPROVEMENTS
|
37,764.00
|
CAVAN COLLEGE OF FURTHER STUDIES
|
EXTERNAL ENVIRONMENT PROJECTS
|
79,795.00
|
ST AIDANS COMPREHENSIVE SCHOOL, COOTEHILLE
|
WINDOW PROJECTS
|
226,266.35
|
BAILIEBORO COMMUNITY SCHOOL
|
OTHER STRUCTURAL IMPROVEMENTS
|
259,592.22
|
TOTAL CAVAN
|
|
928,586.42
|
CLARE
|
|
|
SCOIL MHUIRE ENNISTYMON
|
ROOF WORKS
|
175,315.33
|
MARY IMMACULATE S S LISDOONVARNA
|
ROOF WORKS
|
131,177.91
|
ST JOSEPHS SPANISH POINT, MILTOWN MALBAY
|
OTHER STRUCTURAL IMPROVEMENTS
|
275,901.00
|
ST JOSEPHS, TULLA
|
MECHANICAL WORKS
|
17,059.69
|
ENNIS COMMUNITY COLLEGE
|
PROJECTS-SPECIAL NEEDS FACILITIES
|
337,206.20
|
ENNISTYNOM VS
|
ELECTRICAL WORKS
|
157,058.38
|
ST JOSEPHS COMMUNITY COLLEGE, KILKEE
|
TOILET FACILITIES
|
54,438.00
|
SCARIFF COMMUNITY CLOOEGE
|
ROOF WORKS
|
232,100.46
|
ST ANNES KILLALOE
|
WINDOW PROJECTS
|
178,807.58
|
ST PATRICKS SHANNON
|
WINDOW PROJECTS
|
466,909.80
|
KILRUSH COMMUNITY SCHOOL
|
ROOF WORKS
|
44,565.78
|
TOTAL CLARE
|
|
2,070,540.13
|
CORK
|
|
|
BALLINORA NS
|
WINDOW PROJECTS
|
—
|
ARDSCOIL UI URMOLTAIGH
|
WINDOW PROJECTS
|
22,982.40
|
BANDON GRAMMAR SCHOOL
|
OTHER STRUCTURAL IMPROVEMENTS
|
341,919.54
|
SCOIL MHUIRE GAN SMAL
|
WINDOW PROJECTS
|
28,358.69
|
COLAISTE CHROI NAOFA
|
TOILET FACILITIES
|
70,300.00
|
ST ALOYSIUS COLLEGE
|
WINDOW PROJECTS
|
100,000.00
|
SACRED HEART CLONAKILTY
|
EXTERNAL ENVIRONMENT PROJECTS
|
53,800.00
|
COLAISTE MHUIRE COBH
|
OTHER STRUCTURAL IMPROVEMENTS
|
162,454.75
|
LORETO SECONDARY SCHOOL
|
ELECTRICAL WORKS
|
219,766.00
|
COLAISTE AN PHIARSAIGH
|
ROOF WORKS
|
10,723.05
|
MIDLETON COLLEGE
|
ROOF WORKS
|
109,145.87
|
ST MARYS HIGH SCHOOL, MIDLETON
|
WINDOW PROJECTS
|
133,162.90
|
CHRISTIAN BROTHERS, MITCHELSTOWN
|
MECHANICAL WORKS
|
21,887.56
|
PRESENTATION SECONDARY SCHOOL CORK, MITCHELSTOWN
|
EXTERNAL ENVIRONMENT PROJECTS
|
79,759.05
|
ST FRANCIS CAPUCHIN COLLEGE, ROCHESTOWN
|
TOILET FACILITIES
|
78,640.00
|
MOUNT ST MICHAEL, ROSSCARBERY
|
MECHANICAL WORKS
|
229,276.00
|
MERCY HEIGHTS SECONDARD SCHOOL, SKIBBEREEN
|
WINDOW PROJECTS
|
76,341.30
|
GAELCHOLAISTE MHUIRE NORTH MONASTERY
|
EXTERNAL ENVIRONMENT PROJECTS
|
18,431.00
|
DEERPARK CBS CORK
|
PROJECTS-SPECIAL NEEDS FACILITIES
|
157,541.00
|
COLAISTE CHROI RI, CAPWELL ROAD
|
ROOF WORKS
|
48,936.23
|
ST VINCENTS SECONDARY SCHOOL, ST MARYS ROAD
|
MECHANICAL WORKS
|
64,666.29
|
NORTH PRESENTATION, FARRANREE
|
WINDOW PROJECTS
|
108,171.88
|
ST ALOYSIUS
|
ELECTRICAL WORKS
|
161,364.73
|
MOUNT MERCY COLLEGE, MODEL FARM ROAD
|
ELECTRICAL WORKS
|
101,242.44
|
REGINA MUNDI, DOUGLAS ROAD
|
OTHER STRUCTURAL IMPROVEMENTS
|
100,000.00
|
COLAISTE GHOBNATAN
|
EXTERNAL ENVIRONMENT PROJECTS
|
36,209.00
|
SCOIL MHUIRE BALLINGEARY
|
CURRICULAR REQUIREMENTS
|
117,584.48
|
CLONAKILTY COMMUNITY COLLEGE
|
OTHER STRUCTURAL IMPROVEMENTS
|
173,688.29
|
COACHFORD C C
|
TOILET FACILITIES
|
137,490.00
|
CARRIGHNAFOY C C
|
OTHER STRUCTURAL IMPROVEMENTS
|
97,983.66
|
COLAISTE AN CHRAOIBHIN, FERMOY
|
ROOF WORKS
|
336,018.00
|
COLAISTE TREASA, KANTURK
|
EXTERNAL ENVIRONMENT PROJECTS
|
99,249.41
|
DAVIS COLLEGE MALLOW
|
TOILET FACILITIES
|
216,710.00
|
MCEGAN COLLEGE, MACROOM
|
OTHER STRUCTURAL IMPROVEMENTS
|
75,861.24
|
ST FANAHANS COLLEGE
|
OTHER STRUCTURAL IMPROVEMENTS
|
110,084.72
|
SCHULL COMMUNITY COLLEGE, COLLA ROAD
|
OTHER STRUCTURAL IMPROVEMENTS
|
94,565.00
|
NAGLE COMMUNITY COLLEGE, BLACKROCK
|
OTHER STRUCTURAL IMPROVEMENTS
|
116,438.22
|
COLLEGE OF COMMERCE, MORRISON’S BLACKROCK
|
WINDOW PROJECTS
|
51,467.66
|
ST JOHNS CENTRAL COLLEGE, SAWMILL STREET
|
WINDOW PROJECTS
|
81,407.43
|
COLAISTE STIOFAN NAOFA
|
WINDOW PROJECTS
|
119,668.53
|
TERENCE MACSWEENEY COLLEGE, KNOCKNAHEENY
|
ELECTRICAL WORKS
|
179,585.23
|
COLAISTE DAIBHAID, AN T-ARDAN THEAS
|
CURRICULAR REQUIREMENTS
|
167,240.15
|
ASHTON SCHOOL, BLACKROCK
|
WINDOW PROJECTS
|
142,639.22
|
BOHERBUE COMPREHENSIVE SCHOOL
|
EXTERNAL ENVIRONMENT PROJECTS
|
68,117.57
|
BEARA COMMUNITY SCHOOL
|
OTHER STRUCTURAL IMPROVEMENTS
|
29,500.00
|
MILLSTREET COMMUNITY SCHOOL
|
ROOF WORKS
|
236,177.13
|
ST PETERS COMMUNITY COLLEGE, PASSAGE WEST
|
EXTERNAL ENVIRONMENT PROJECTS
|
141,558.83
|
DOUGLAS COMMUNITY SCHOOL
|
TOILET FACILITIES
|
29,285.82
|
BISHOPSTOWN C S
|
ELECTRICAL WORKS
|
335,150.03
|
TOTAL CORK
|
|
5,692,550.30
|
DONEGAL
|
|
|
SCOIL MHUIRE BUNCRANA
|
CURRICULAR REQUIREMENTS
|
178,355.00
|
LORETO SECONDARY SCHOOL
|
OTHER STRUCTURAL IMPROVEMENTS
|
28,000.00
|
ST COLUMBAS COLLEGE, LIFFORD
|
TOILET FACILITIES
|
60,020.00
|
CRANA COLLEGE
|
EXTERNAL ENVIRONMENT PROJECTS
|
81,950.50
|
ABBEY V S
|
EXTERNAL ENVIRONMENT PROJECTS
|
125,235.57
|
DEELE COLLEGE, RAPHOE
|
OTHER STRUCTURAL IMPROVEMENTS
|
324,319.00
|
ST CATHERINES VOCATIONAL SCHOOL, KILLYBEGS
|
EXTERNAL ENVIRONMENT PROJECTS
|
97,790.00
|
GAIRMSCOIL MHIC DIARMADA
|
EXTERNAL ENVIRONMENT PROJECTS
|
66,156.00
|
MOVILLE COMMUNITY COLLEGE
|
MECHANICAL WORKS
|
35,297.55
|
CARNDONAGH COMMUNITY SCHOOL
|
ROOF WORKS
|
461,991.28
|
ROSSES COMMUNITY SCHOOL
|
EXTERNAL ENVIRONMENT PROJECTS
|
124,560.84
|
POBALSCOIL CHLOICH CHEANNFHAOLA
|
WINDOW PROJECTS
|
335,955.01
|
GWEEDORE COMMUNITY SCHOOL
|
WINDOW PROJECTS
|
53,746.24
|
BALLYSHANNON COMMUNITY SCHOOL
|
OTHER STRUCTURAL IMPROVEMENTS
|
—
|
TOTAL DONEGAL
|
|
1,973,376.99
|
DUBLIN
|
|
|
BLACKROCK COLLEGE DUBLIN
|
ROOF WORKS
|
131,650.00
|
COLAISTE EOIN AGUS IOSAGAIN, STILORGAN
|
OTHER STRUCTURAL IMPROVEMENTS
|
35,241.70
|
COLAISTE IOSAGAIN, BAILE AN BHOTHAIR
|
WINDOW PROJECTS
|
50,825.30
|
OATLANDS COLLEGE, MOUNT MERRION
|
ROOF WORKS
|
218,945.00
|
DOMINICAN COLLEGE, SION HILL, BLACKROCK
|
ROOF WORKS
|
248,966.87
|
ROCKFORD MANOR S.S., STRADBROOK ROAD, BLACKROCK
|
WINDOW PROJECTS
|
162,000.00
|
CASTLEKNOCK COLLEGE
|
OTHER STRUCTURAL IMPROVEMENTS
|
—
|
MOYLE PARK COLLEGE, CLONDALKIN
|
ROOF WORKS
|
211,000.00
|
MOUNT ANVILLE SECONDARY SCHOOL
|
MECHANICAL WORKS
|
48,466.57
|
NOTRE DAME DES MISSIONS, UPPER CHURCHTOWN ROAD
|
MECHANICAL WORKS
|
14,850.00
|
HOLY CHILD KILLINEY, MILITARY ROAD KILLINEY
|
WINDOW PROJECTS
|
106,478.00
|
ST JOSEPHS OF CLUNY, BELLEVUE PARK, BALLINCLEA ROAD
|
MECHANICAL WORKS
|
13,750.00
|
ST BENILDUS COLLEGE, UPPER KILMACUD RD, BLACKROCK
|
TOILET FACILITIES
|
203,500.00
|
ST LAURENCES COLLEGE, LOUGHLINSTOWN, DUBLIN 18
|
ELECTRICAL WORKS
|
328,702.00
|
ST JOSEPHS LUCAN
|
CURRICULAR REQUIREMENTS
|
75,600.00
|
COLAISTE PHADRAIG CBS, ROSELAWN
|
CURRICULAR REQUIREMENTS
|
238,441.46
|
THE KINGS HOSPITAL, PALMERSTOWN
|
WINDOW PROJECTS
|
276,019.00
|
ST PAULS COLLEGE, RAHENY
|
OTHER STRUCTURAL IMPROVEMENTS
|
76,217.17
|
ARD SCOIL LA SALLE
|
EXTERNAL ENVIRONMENT PROJECTS
|
34,950.85
|
MANOR HOUSE RAHENY, WATERMILL ROAD, RAHENY
|
WINDOW PROJECTS
|
195,927.00
|
DE LA SALLE CHURCHTOWN
|
MECHANICAL WORKS
|
446,384.60
|
LORETO HIGH SCHOOL
|
WINDOW PROJECTS
|
21,450.00
|
COLAISTE EANNA CBS, RATHFARNHAM
|
ELECTRICAL WORKS
|
113,320.37
|
ST RAPHAELAS, STILLORGAN
|
TOILET FACILITIES
|
77,511.58
|
ST FINTANS HIGH SCHOOL, SUTTON
|
ROOF WORKS
|
171,417.80
|
ST JAMES CBS, JAMES’S STREET
|
TOILET FACILITIES
|
103,937.00
|
CBS SYNGE STREET
|
MECHANICAL WORKS
|
261,126.87
|
ST DAVIDS CBS, ARTANE
|
ROOF WORKS
|
196,721.39
|
MEANSCOIL IOGNAID RIS, WALKINSTOWN
|
TOILET FACILITIES
|
182,193.00
|
ST DECLANS COLLEGE, CABRA
|
TOILET FACILITIES
|
49,292.35
|
MARIAN COLLEGE, BALLSBRIDGE
|
CURRICULAR REQUIREMENTS
|
184,830.00
|
ST JOHNS COLLEGE DE LA SALLE BALLYFERMOT
|
TOILET FACILITIES
|
96,007.60
|
CHANEL COLLEGE COOLOCK
|
WINDOW PROJECTS
|
143,414.63
|
TEMPLEOGUE COLLEGE
|
ROOF WORKS
|
87,941.26
|
PATRICIAN COLLEGE, FINGLAS WEST
|
CURRICULAR REQUIREMENTS
|
115,301.30
|
ST KEVINS COLLEGE, EAST FINGLAS
|
ELECTRICAL WORKS
|
197,712.80
|
ST PATRICKS CATHEDRAL GRAMMAR SCHOOL, ST PATRICKS CLOSE
|
TOILET FACILITIES
|
35,417.32
|
THE HIGH SCHOOL RATHGAR
|
ROOF WORKS
|
99,125.00
|
SCOIL CATRIONA MOBHI ROAD
|
MECHANICAL WORKS
|
106,467.15
|
ST DOMINIC’S, BALLYFERMOT
|
TOILET FACILITIES
|
179,182.80
|
ST DOMINIC’S COLLEGE CABRA
|
OTHER STRUCTURAL IMPROVEMENTS
|
26,631.74
|
CARITAS COLLEGE, BALLYFERMOT
|
ROOF WORKS
|
47,384.95
|
ST MICHAEL’S HOLY FAITH, FINGLAS
|
CURRICULAR REQUIREMENTS
|
250,148.00
|
HOLY FAITH, CLONTARF
|
ROOF WORKS
|
133,298.18
|
ST MARYS GLASNEVIN
|
OTHER STRUCTURAL IMPROVEMENTS
|
43,363.12
|
PRESENTATION CONVENT WARRENMOUNT
|
TOILET FACILITIES
|
100,000.00
|
LORETO COLLEGE CRUMLIN
|
CURRICULAR REQUIREMENTS
|
82,139.00
|
LORETO SWORDS
|
WINDOW PROJECTS
|
89,805.00
|
LORETO COLLEGE, ST STEPHEN’S GREEN
|
CURRICULAR REQUIREMENTS
|
—
|
MARYFIELD COLLEGE, DRUMCONDRA
|
OTHER STRUCTURAL IMPROVEMENTS
|
390,000.00
|
ST JOSEPHS SECONDARY SCHOOL, STANHOPE STREET
|
MECHANICAL WORKS
|
181,158.63
|
MERCY COLLEGE COOLOCK
|
CURRICULAR REQUIREMENTS
|
130,052.60
|
MERCY SECONDARY SCHOOL, INCHICORE
|
ROOF WORKS
|
254,475.51
|
ST LOUIS HIGH SCHOOL, RATHMINES
|
CURRICULAR REQUIREMENTS
|
208,762.41
|
ST PAULS SECONDARY SCHOOL, GREENHILLS
|
CURRICULAR REQUIREMENTS
|
135,110.00
|
ALEXANDRA COLLEGE, MILLTOWN
|
ROOF WORKS
|
167,066.77
|
OUR LADY OF MERCY DRIMNAGH
|
CURRICULAR REQUIREMENTS
|
92,282.00
|
WESLEY COLLEGE, BALLINTEER
|
MECHANICAL WORKS
|
45,019.00
|
STRATFORD COLLEGE, RATHGAR
|
WINDOW PROJECTS
|
25,069.76
|
BALBRIGGAN C C
|
MECHANICAL WORKS
|
—
|
COLAISTE DE HIDE TALLAGHT
|
ROOF WORKS
|
72,802.88
|
DEANSRATH COMMUNITY COLLEGE, CLONDALKIN
|
MECHANICAL WORKS
|
292,808.43
|
COLLINSTOWN PARK COMMUNITY COLLEGE, CLONDALKIN
|
WINDOW PROJECTS
|
117,863.67
|
ST KEVINS COMMUNITY COLLEGE, CLONDALKIN
|
MECHANICAL WORKS
|
192,315.85
|
DUN LAOGHAIRE COLLEGE OF FURTHER EDUCATION
|
MECHANICAL WORKS
|
15,910.00
|
LUCAN V S
|
WINDOW PROJECTS
|
65,976.97
|
RIVERSDALE COMMUNITY COLLEGE, BLANCHARDSTOWN
|
MECHANICAL WORKS
|
251,205.94
|
COLAISTE CHILLIAN
|
MECHANICAL WORKS
|
191,532.58
|
STILLORGAN COLLEGE OF FURTHER EDUCATION
|
WINDOW PROJECTS
|
104,737.00
|
ST FINIANS C C
|
ROOF WORKS
|
—
|
FINGAL COMMUNITY COLLEGE
|
ELECTRICAL WORKS
|
71,791.35
|
GREENHILLS COLLEGE
|
MECHANICAL WORKS
|
232,950.05
|
FIRHOUSE COMMUNITY COLLEGE
|
WINDOW PROJECTS
|
186,846.35
|
JOBSTOWN COMMUNITY COLLEGE
|
ROOF WORKS
|
140,000.00
|
ST KEVINS COMMUNITY COLLEGE, CRUMLIN
|
TOILET FACILITIES
|
16,629.38
|
CRUMLIN COLLEGE OF FURTHER EDUCATION
|
TOILET FACILITIES
|
58,350.49
|
COLAISTE EOIN, FINGLAS
|
ELECTRICAL WORKS
|
232,400.17
|
COLAISTE IDE, FINGLAS WEST
|
ELECTRICAL WORKS
|
400,157.91
|
RINGSEND TECHNICAL INSTITUTE
|
MECHANICAL WORKS
|
102,020.22
|
KILLESTER COLLEGE OF FURTHER EDUCATION
|
MECHANICAL WORKS
|
270,871.08
|
KYLEMORE COLLEGE BALLYFERMOT
|
TOILET FACILITIES
|
88,835.68
|
MARION COLLEGE, FAIRVIEW
|
TOILET FACILITIES
|
106,464.61
|
ST MACDARAS COMMUNITY COLLEGE, TEMPLEOGUE
|
TOILET FACILITIES
|
215,375.93
|
RATHMINES SENIOR COLLEGE
|
OTHER STRUCTURAL IMPROVEMENTS
|
127,215.40
|
BALLSBRIDGE COLLEGE OF BUSINESS STUDIES
|
MECHANICAL WORKS
|
191,260.75
|
PEARSE COLLEGE, CRUMLIN
|
TOILET FACILITIES
|
174,915.00
|
PLUNKET COLLEGE, WHITEHALL
|
ROOF WORKS
|
94,217.06
|
WHITEHALL HSE SEN SCHOOL
|
EXTERNAL ENVIRONMENT PROJECTS
|
66,871.43
|
MARGARET AYLWARD COLLEGE
|
WINDOW PROJECTS
|
145,706.00
|
COLAISTE DHULAIGH, COOLOCK
|
ELECTRICAL WORKS
|
234,466.62
|
LIBERTIES COLLEGE
|
WINDOW PROJECTS
|
186,481.69
|
BALLYFERMOT COLLEGE OF FURTHER EDUCATION
|
MECHANICAL WORKS
|
241,746.13
|
COLAISTE LAN GAEILGE AN GHRAINSEACH
|
ROOF WORKS
|
110,420.94
|
PRESENTATION COLLEGE TERENURE
|
TOILET FACILITIES
|
81,248.44
|
TRINITY COMPREHENSIVE
|
ROOF WORKS
|
237,796.88
|
SCOIL PHOBAIL CHUIL MHIN
|
CURRICULAR REQUIREMENTS
|
311,728.52
|
THE DONAHIES COMMUNITY SCHOOL, STREAMVILLE ROAD
|
WINDOW PROJECTS
|
232,820.87
|
PORTMARNOCK COMMUNITY SCHOOL
|
CURRICULAR REQUIREMENTS
|
72,360.04
|
MALAHIDE COMMUNITY SCHOOL
|
MECHANICAL WORKS
|
147,578.70
|
HOLY CHILD C S SALLYNOGGIN
|
WINDOW PROJECTS
|
57,295.86
|
ST MARKS SPRINGFIELD, TALLAGHT
|
WINDOW PROJECTS
|
200,221.93
|
TALLAGHT COMMUNITY SCHOOL
|
TOILET FACILITIES
|
29,944.79
|
OLD BAWN COMMUNITY SCHOOL, TALLAGHT
|
WINDOW PROJECTS
|
249,952.30
|
ST AIDENS BROOKFIELD, TALLAGHT
|
CURRICULAR REQUIREMENTS
|
68,519.70
|
ST TIERNANS COMMUNITY COLLEGE, BALALLY
|
ELECTRICAL WORKS
|
203,487.35
|
TOTAL DUBLIN
|
|
14,836,155.35
|
GALWAY
|
|
|
PRESENTATION COLLEGE, ATHENRY
|
EXTERNAL ENVIRONMENT PROJECTS
|
178,000.00
|
ST JOSEPHS GARBALLY
|
WINDOW PROJECTS
|
188,842.00
|
COLAISTE MHUIRE, BALLYGAR
|
EXTERNAL ENVIRONMENT PROJECTS
|
113,500.00
|
ST JOSEOHS NUNS ISLAND
|
CURRICULAR REQUIREMENTS
|
266,640.40
|
DOMINICAN COLLEGE TAYLORS’ HILL
|
MECHANICAL WORKS
|
91,303.00
|
JESUS & MARY SECONDARY SCHOOL, THREADNEEDLE ROAD
|
ROOF WORKS
|
52,300.00
|
PRESENTATION COLLEGE, HEADFORD
|
TOILET FACILITIES
|
60,980.23
|
HOLY ROSARY COLLEGE, MOUNTBELLEW
|
TOILET FACILITIES
|
177,000.00
|
CALASANCTIUS COLLEGE ORANMORE
|
EXTERNAL ENVIRONMENT PROJECTS
|
35,056.00
|
ST JARLATH’S COLLEGE, TUAM
|
TOILET FACILITIES
|
—
|
ST BRIGID’S TUAM
|
ROOF WORKS
|
110,160.00
|
PRESENTATION COLLEGE CURRYLEA
|
WINDOW PROJECTS
|
174,000.00
|
ST JARLATHS COLLEGE
|
TOILET FACILITIES
|
94,024.64
|
ST JARLATHS VOCATIONAL SCHOOL, MOUNTBELLEW
|
EXTERNAL ENVIRONMENT PROJECTS
|
49,045.00
|
GAIRM SCOIL CHILLEAIN NAOFA, BALLINASLOE
|
ROOF WORKS
|
56,000.00
|
GAIRMSCOIL FHEICHIN NAOFA
|
MECHANICAL WORKS
|
54,186.00
|
COLAISTE GHOBNAIT INIS OIRR
|
MECHANICAL WORKS
|
77,756.11
|
GALWAY COMMUNITY COLLEGE, WELLPARK
|
WINDOW PROJECTS
|
171,441.92
|
SCOIL CHUIMSITHEACH CHIARAIN, AN CHEATHRU RUA
|
TOILET FACILITIES
|
70,540.68
|
TOTAL GALWAY
|
|
2,020,775.98
|
KERRY
|
|
|
ST JOSEPHS SECONDARY SCHOOL, BALLYBUNION
|
MECHANICAL WORKS
|
58,528.84
|
MEANSCOIL PHADRAIG NAOFA, CASTLEISLAND
|
TOILET FACILITIES
|
54,736.59
|
MEAN SCOIL NAOMH JOSEPH, CASTLEISLAND
|
ROOF WORKS
|
214,362.00
|
ST BRENDANS COLLEGE, CILL AIRNE
|
WINDOW PROJECTS
|
221,650.20
|
INTERMEDIATE SCHOOL KILLORGLIN
|
ELECTRICAL WORKS
|
73,440.00
|
ST MICHAELS COLLEGE
|
WINDOW PROJECTS
|
189,648.48
|
PRESENTATION S.S. MILLTOWN, KILLARNEY
|
ELECTRICAL WORKS
|
100,000.00
|
PRESENTATION SECONDARY SCHOOL TRALEE
|
EXTERNAL ENVIRONMENT PROJECTS
|
50,000.00
|
MOUNT HAWK SCHOOL, TRALEE
|
EXTERNAL ENVIRONMENT PROJECTS
|
234,239.39
|
KILLORGLIN C C
|
ROOF WORKS
|
267,000.00
|
LISTOWEL COMMUNITY COLLEGE
|
PROJECTS-SPECIAL NEEDS FACILITIES
|
58,800.00
|
CASTLEISLAND V S
|
ELECTRICAL WORKS
|
16,227.40
|
CAUSEWAY C C, TRALEE
|
MECHANICAL WORKS
|
59,500.00
|
TRALEE CC
|
ELECTRICAL WORKS
|
410,000.00
|
GAELCHOLAISTE CHIARRAI, TRALEE
|
PROJECTS-SPECIAL NEEDS FACILITIES
|
—
|
RATHMORE COMMUNITY SCHOOL
|
MECHANICAL WORKS
|
21,964.52
|
DINGLE CS
|
EXTERNAL ENVIRONMENT PROJECTS
|
722.93
|
TOTAL KERRY
|
|
2,030,820.35
|
KILDARE
|
|
|
SALESIAN SECONDARY SCHOOL, CELLBRIDGE
|
ROOF WORKS
|
264,930.40
|
CROSS AND PASSION COLLEGE, KILCULLEN
|
ELECTRICAL WORKS
|
216,000.00
|
SCOIL DARA KILCOCK
|
TOILET FACILITIES
|
41,200.00
|
ST PAUL’S MONASTEREVIN
|
ROOF WORKS
|
146,932.97
|
COLAISTE NAOMH MHUIRE, NAAS
|
WINDOW PROJECTS
|
222,575.75
|
CURRAGH POST PRIMARY
|
OTHER STRUCTURAL IMPROVEMENTS
|
11,371.00
|
COLAISTE LORCAIN CASTLEDERMOT
|
WINDOW PROJECTS
|
240,279.00
|
VOCATIONAL SCHOOL KILDARE COLLEGE OF FURTHER STUDIES
|
WINDOW PROJECTS
|
89,421.26
|
CONFEY COMMUNITY COLLEGE
|
WINDOW PROJECTS
|
194,500.00
|
ST FARNANS POST PRIMARY SCHOOL, PROSPEROUS
|
TOILET FACILITIES
|
21,600.00
|
RATHANGAN POST PRIMARY SCHOOL
|
OTHER STRUCTURAL IMPROVEMENTS
|
—
|
TOTAL KILDARE
|
|
1,448,810.38
|
KILKENNY
|
|
|
COLAISTE EAMANN RIS, CALLAN
|
MECHANICAL WORKS
|
42,524.00
|
CBS KILKENNY
|
ELECTRICAL WORKS
|
100,823.72
|
ST KIERANS COLLEGE KILKENNY
|
CURRICULAR REQUIREMENTS
|
140,607.40
|
KILKENNY COLLEGE
|
MECHANICAL WORKS
|
62,334.49
|
COLAISTE AIREAGAIL BALLYHALE
|
CURRICULAR REQUIREMENTS
|
23,156.07
|
DUISKE COLLEGE GRAIGNAMANAGH
|
OTHER STRUCTURAL IMPROVEMENTS
|
34,100.00
|
COLAISTE MHUIRE JOHNSTOWN VS
|
OTHER STRUCTURAL IMPROVEMENTS
|
51,500.00
|
CITY TECHNICAL SCHOOL, NEW STREET, KILKENNY
|
ROOF WORKS
|
200,000.00
|
CASTLECOMER COMMUNITY SCHOOL
|
ROOF WORKS
|
177,981.35
|
TOTAL KILKENNY
|
|
833,027.03
|
LAOIS
|
|
|
CLONASLEE VOCATIONAL SCHOOL
|
EXTERNAL ENVIRONMENT PROJECTS
|
34,977.45
|
MOUNTMELLICK COMMUNITY SCHOOL
|
CURRICULAR REQUIREMENTS
|
83,565.21
|
HEYWOOD COMMUNITY SCHOOL, BALLINAKILL
|
WINDOW PROJECTS
|
104,792.37
|
TOTAL LAOIS
|
|
223,335.03
|
LEITRIM
|
|
|
CARRIGALLEN V S
|
ROOF WORKS
|
83,474.00
|
DRUMKEERIN VS
|
TOILET FACILITIES
|
72,669.03
|
DRUMSHAMBO V.S.
|
TOILET FACILITIES
|
161,360.85
|
SCOIL CHUIMSITHEACH NAOMH CLAR
|
TOILET FACILITIES
|
63,146.76
|
TOTAL LEITRIM
|
|
380,650.64
|
LIMERICK
|
|
|
SALEASIAN SECONDARY SCHOOL, PALLASKENRY
|
WINDOW PROJECTS
|
89,075.00
|
PRESENTATION CONVENT, SEXTON STREET
|
TOILET FACILITIES
|
81,664.35
|
LAUREL HILL, NORTH CIRCULAR ROAD
|
EXTERNAL ENVIRONMENT PROJECTS
|
76,469.00
|
SALESIAN SEC SCHOOL, NORTH CIRCULAR ROAD
|
MECHANICAL WORKS
|
30,236.12
|
ARD SCOIL MHUIRE CORBALLY
|
CURRICULAR REQUIREMENTS
|
148,278.00
|
SCOIL CARMEL LIMERICK, O’CONNELL AVENUE
|
MECHANICAL WORKS
|
50,353.28
|
ASKEATON COMMUNITY COLLEGE
|
EXTERNAL ENVIRONMENT PROJECTS
|
4,375.00
|
DESMOND COLLEGE, NEWCASTLEWEST
|
OTHER STRUCTURAL IMPROVEMENTS
|
37,750.00
|
LIMERICK SENIOR COLLEGE, MULGRADE STREET
|
WINDOW PROJECTS
|
56,787.94
|
MERCY C C RATHKEALE VS
|
MECHANICAL WORKS
|
36,699.76
|
COLAISTE IOSAEF, KILMALLOCK
|
EXTERNAL ENVIRONMENT PROJECTS
|
17,755.98
|
CRESCENT COLLEGE COMPREHENSIVE, DOORADOYLE
|
WINDOW PROJECTS
|
227,300.72
|
JOHN THE BAPTIST COMMUNITY SCHOOL
|
ROOF WORKS
|
108,205.75
|
TOTAL LIMERICK
|
|
964,950.90
|
LONGFORD
|
|
|
CNOC MHUIRE, GRANARD
|
WINDOW PROJECTS
|
72,300.00
|
ARDSCOIL PHADRAIG, GRANARD
|
WINDOW PROJECTS
|
45,704.00
|
TEMPLEMICHAELCOLLEGE
|
WINDOW PROJECTS
|
73,334.00
|
MOYNE C S
|
ROOF WORKS
|
295,438.82
|
TOTAL LONGFORD
|
|
486,776.82
|
LOUTH
|
|
|
ST JOSEPHS, DROGHEDA
|
ELECTRICAL WORKS
|
378,767.43
|
OUR LADY’S COLLEGE GREENHILLS, DROGHEDA
|
EXTERNAL ENVIRONMENT PROJECTS
|
79,969.00
|
COLAISTE RIS, DUN DEALGAN
|
CURRICULAR REQUIREMENTS
|
358,533.42
|
ST MARY’S COLLEGE, DUNDALK
|
TOILET FACILITIES
|
154,362.12
|
DE LA SALLE COLLEGE
|
ROOF WORKS
|
573,600.00
|
ST VINCENTS SECONDARY SCHOOL
|
ROOF WORKS
|
64,874.34
|
BUSH POST PRIMARY CC, DUNDALK
|
WINDOW PROJECTS
|
243,363.08
|
ST OLIVERS COMMUNITY COLLEGE
|
ELECTRICAL WORKS
|
500,000.00
|
OFIAICH COLLEGE, DUNDALK
|
CURRICULAR REQUIREMENTS
|
213,775.10
|
SCOIL UI MHUIRE, DUNLEER
|
TOILET FACILITIES
|
138,384.81
|
ARDEE COMMUNITY SCHOOL
|
WINDOW PROJECTS
|
365,583.83
|
TOTAL LOUTH
|
|
3,071,213.13
|
MAYO
|
|
|
ST MURDEACHS COLLEGE, BALLINA
|
MECHANICAL WORKS
|
342,200.00
|
OUR LADYS SECONDARY SCHOOL, BELMULLET
|
WINDOW PROJECTS
|
157,555.07
|
ST JOSEPH’S S S, CASTLEBAR
|
CURRICULAR REQUIREMENTS
|
54,834.45
|
ST JOSEPH’S SECONDARY SCHOOL, MARIST CONVENT
|
TOILET FACILITIES
|
14,500.00
|
ST COLMANS COLLEGE, SWINFORD
|
ROOF WORKS
|
194,753.00
|
ST JOSEPHS SECONDARY SCHOOL
|
ROOF WORKS
|
205,161.62
|
COLAISTE MHUIRE, TUAR MHIC EADAIGH
|
WINDOW PROJECTS
|
36,205.07
|
RICE COLLEGE WESTPORT
|
OTHER STRUCTURAL IMPROVEMENTS
|
25,400.00
|
SACRED HEART, WESTPORT
|
ROOF WORKS
|
39,458.75
|
MOYNE V S, BALLINA
|
OTHER STRUCTURAL IMPROVEMENTS
|
33,286.33
|
MC HALE COLLEGE ACHILL
|
WINDOW PROJECTS
|
58,563.32
|
ST TIERNAN’S COLLEGE, CROSSMOLINA
|
TOILET FACILITIES
|
144,000.00
|
WESTPORT V.S.
|
TOILET FACILITIES
|
50,947.31
|
DAVITT COLLEGE CASTLEBAR
|
TOILET FACILITIES
|
86,400.00
|
BALLYHAUNIS COMMUNITY SCHOOL
|
EXTERNAL ENVIRONMENT PROJECTS
|
26,149.98
|
BALLINROBE COMMUNITY SCHOOL
|
WINDOW PROJECTS
|
43,985.55
|
ST LOUIS COMMUNITY SCHOOL
|
EXTERNAL ENVIRONMENT PROJECTS
|
59,485.61
|
TOTAL MAYO
|
|
1,572,886.06
|
MEATH
|
|
|
ST PATRICKS CLASSICAL, MOATLANDS
|
OTHER STRUCTURAL IMPROVEMENTS
|
49,130.00
|
ST JOSEPHS SECONDARY SCHOOL NAVAN
|
EXTERNAL ENVIRONMENT PROJECTS
|
346,031.43
|
EUREKA SECONDARY SCHOOL
|
OTHER STRUCTURAL IMPROVEMENTS
|
107,777.45
|
SCOIL MHUIRE COM TRIM
|
ELECTRICAL WORKS
|
296,437.83
|
ST PETER’S COLLEGE, DUNBOYNE
|
WINDOW PROJECTS
|
196,627.00
|
ST OLIVERS POST PRIMARY, KELLS
|
EXTERNAL ENVIRONMENT PROJECTS
|
13,746.65
|
COLAISTE PHOBAIL
|
ROOF WORKS
|
205,997.17
|
BEAUFORT NAVAN
|
ROOF WORKS
|
159,572.15
|
RATHOATH C C
|
EXTERNAL ENVIRONMENT PROJECTS
|
87,000.00
|
ASHBOURNE COMMUNITY SCHOOL
|
ROOF WORKS
|
540,654.42
|
TOTAL MEATH
|
|
2,002,974.10
|
MONAGHAN
|
|
|
ST LOUIS SS CARRICKMACROSS
|
ELECTRICAL WORKS
|
395,594.94
|
OUR LADYS SEC SCHOOL, CASTLEBLANEY
|
ELECTRICAL WORKS
|
214,002.00
|
ST McCARTANS COLLEGE
|
TOILET FACILITIES
|
172,041.78
|
ST LOUIS S.S. MONAGHAN
|
OTHER STRUCTURAL IMPROVEMENTS
|
40,170.74
|
MONAGHAN COLLEGIATE, CORLATT
|
TOILET FACILITIES
|
116,252.50
|
BALLYBAY COMMUNITY COLLEGE
|
OTHER STRUCTURAL IMPROVEMENTS
|
662,178.81
|
CASTLEBLANEY COLLEGE
|
TOILET FACILITIES
|
273,359.19
|
BEECHILL V S
|
CURRICULAR REQUIREMENTS
|
430,652.43
|
TOTAL MONAGHAN
|
|
2,304,252.39
|
OFFALY
|
|
|
ST MARYS SECONDARY SCHOOL, EDENDERRY
|
ROOF WORKS
|
270,000.00
|
SACRED HEART SECONDARY SCHOOL, TULLAMORE
|
OTHER STRUCTURAL IMPROVEMENTS
|
100,400.00
|
KILLINA, RAHAN, TULLAMORE
|
ROOF WORKS
|
69,448.00
|
CLARA V S
|
ELECTRICAL WORKS
|
52,949.75
|
OAKLANDS COLLEGE, EDENDERRY
|
ROOF WORKS
|
205,876.97
|
TOTAL OFFALY
|
|
698,674.72
|
ROSCOMMON
|
|
|
ELPHIN V S
|
ROOF WORKS
|
21,930.00
|
ROSCOMMON C C
|
CURRICULAR REQUIREMENTS
|
94,826.55
|
CASTLEREA C.S.
|
EXTERNAL ENVIRONMENT PROJECTS
|
27,240.00
|
TOTAL ROSCOMMON
|
|
143,996.55
|
SLIGO
|
|
|
ST MARYS COLLEGE, BALLYSADARE
|
ROOF WORKS
|
39,665.20
|
COLAISTE MHUIRE, BALLYMOTE
|
ROOF WORKS
|
46,859.26
|
JESUS & MARY, ENNISCRONE
|
OTHER STRUCTURAL IMPROVEMENTS
|
181,758.50
|
URSULINE COLLEGE
|
WINDOW PROJECTS
|
36,700.00
|
MERCY COLLEGE SLIGO
|
WINDOW PROJECTS
|
53,143.97
|
SLIGO GRAMMAR SCHOOL, THE MALL
|
EXTERNAL ENVIRONMENT PROJECTS
|
183,000.00
|
COOLA V.S., SOOEY, VIA BOYLE
|
MECHANICAL WORKS
|
120,510.48
|
GRANGE C C
|
ROOF WORKS
|
50,080.18
|
BALLINODE VS
|
EXTERNAL ENVIRONMENT PROJECTS
|
102,878.93
|
TOTAL SLIGO
|
|
814,596.52
|
TIPPERARY
|
|
|
ST JOSEPH’S COLLEGE
|
TOILET FACILITIES
|
17,339.71
|
ROCKWELL COLLEGE
|
ROOF WORKS
|
70,327.59
|
ARD SCOIL NA MBRAITHRE
|
ELECTRICAL WORKS
|
51,070.92
|
LORETO SECONDARY SCHOOL
|
OTHER STRUCTURAL IMPROVEMENTS
|
33,021.00
|
PATRICIAN PRESENATION SECONDARY SCHOOL
|
EXTERNAL ENVIRONMENT PROJECTS
|
53,644.73
|
ST MARY’S SECONDARY SCHOOL NENAGH
|
ROOF WORKS
|
348,377.47
|
CISTERCIAN COLLEGE
|
OTHER STRUCTURAL IMPROVEMENTS
|
50,014.06
|
PRESENTATION SECONDARY SCHOOL
|
MECHANICAL WORKS
|
279,169.36
|
URSULINE SEC SCHOOL
|
ELECTRICAL WORKS
|
66,099.70
|
ST ANNE’S S.S. ROSANNA RD
|
OTHER STRUCTURAL IMPROVEMENTS
|
100,562.75
|
COMERAGH COLLEGE
|
WINDOW PROJECTS
|
92,600.00
|
SCOIL RUAIN
|
ELECTRICAL WORKS
|
56,561.55
|
NEWPORT V S
|
ELECTRICAL WORKS
|
35,629.28
|
ST SHEELANS TEMPLEMORE
|
WINDOW PROJECTS
|
121,940.40
|
TIPPERARY TOWN VS
|
WINDOW PROJECTS
|
157,400.00
|
THURLES VOCATIONAL SCHOOL
|
ELECTRICAL WORKS
|
45,885.17
|
CAHIR COMMUNITY COLLEGE
|
ELECTRICAL WORKS
|
82,441.74
|
ROSCREA COMMUNITY COLLEGE
|
ELECTRICAL WORKS
|
46,132.88
|
TOTAL TIPPERARY
|
|
1,708,218.31
|
WATERFORD
|
|
|
CBS DUNGARVAN
|
OTHER STRUCTURAL IMPROVEMENTS
|
210,600.00
|
ST AUGUSTINES COLLEGE
|
OTHER STRUCTURAL IMPROVEMENTS
|
140,000.00
|
ARD SCOIL NA NDEISE
|
WINDOW PROJECTS
|
106,553.00
|
DE LA SALLE COLLEGE NEWTOWN
|
WINDOW PROJECTS
|
236,555.00
|
OUR LADY OF MERCY SEC SCHOOL WATERFORD
|
MECHANICAL WORKS
|
421,623.31
|
NEWTOWN SCHOOL
|
WINDOW PROJECTS
|
—
|
ST DECLANS KILMACTHOMAS
|
WINDOW PROJECTS
|
61,950.00
|
CENTRAL TECHNICAL INSTITUTE
|
EXTERNAL ENVIRONMENT PROJECTS
|
44,024.00
|
ST PAULS C C
|
ROOF WORKS
|
809,235.47
|
LISMORE COMMUNITY SCHOOL
|
EXTERNAL ENVIRONMENT PROJECTS
|
39,725.00
|
TOTAL WATERFORD
|
|
2,070,265.78
|
WESTMEATH
|
|
|
ST ALOYSIUS COLLEGE
|
ROOF WORKS
|
100,210.05
|
ST JOSEPHS COLLEGE
|
ROOF WORKS
|
17,480.00
|
CONVENT S S KILBEGGAN
|
ROOF WORKS
|
81,017.51
|
ST MARYS COLLEGE MULLINGAR
|
WINDOW PROJECTS
|
128,375.00
|
ST FINIANS COLLEGE
|
OTHER STRUCTURAL IMPROVEMENTS
|
288,020.02
|
ST JOSEPHS SECONDARY SCHOOL
|
WINDOW PROJECTS
|
150,000.00
|
CASTLEPOLLARD COMMUNITY COLLEGE
|
OTHER STRUCTURAL IMPROVEMENTS
|
34,690.50
|
COLUMBA COLLEGE
|
MECHANICAL WORKS
|
228,034.04
|
TOTAL WESTMEATH
|
|
1,027,827.12
|
WEXFORD
|
|
|
FCJ BUNCLODY
|
WINDOW PROJECTS
|
234,000.00
|
ST MARY’S CBS ENNISCORTHY
|
ROOF WORKS
|
196,638.04
|
COLAISTE BRIDE ENNISCORTHY
|
ELECTRICAL WORKS
|
387,232.66
|
CHRISTIAN BROTHERS SS NEW ROSS
|
ELECTRICAL WORKS
|
184,210.50
|
GOOD COUNSEL COLLEGE
|
EXTERNAL ENVIRONMENT PROJECTS
|
97,892.67
|
ST MARYS WEXFORD
|
ROOF WORKS
|
200,000.00
|
OUR LADY OF LOURDES
|
OTHER STRUCTURAL IMPROVEMENTS
|
100,000.00
|
LORETO S.S. SPAWELL RD
|
WINDOW PROJECTS
|
160,172.52
|
PRESENTATION SECONDARY SCHOOL, GROGAN’S ROAD
|
MECHANICAL WORKS
|
391,777.00
|
ADAMSTOWN VS
|
WINDOW PROJECTS
|
140,800.00
|
BRIDGETOWN VS
|
WINDOW PROJECTS
|
179,143.89
|
BUNCLODY VOCATIONAL SCHOOL
|
EXTERNAL ENVIRONMENT PROJECTS
|
44,203.28
|
NEW ROSS VS
|
EXTERNAL ENVIRONMENT PROJECTS
|
93,564.35
|