This is my first visit to this Seanad and I look forward to the discussions that will take place here. I hope to be as accommodating and as forthcoming as possible with all Senators.
The main purposes of the Bill are to increase the authorised share capital of Irish Steel Limited from £25 million to £50 million; to provide, as a consequence, a similar increase in the value of shares which the Minister for Finance may take up; and to provide for an increase in the limit on the Ministerial guarantee of company borrowings from £60 million to £75 million.
Irish Steel Limited are a wholly State-owned company, whose principal activity is the manufacture of steel from scrap. The steel products made are mainly used in the construction industry. The company's only other activity is the manufacture of galvanised sheet of the type used for farm buildings.
I consider it appropriate at this point to give some background to the present state of the company, which creates the need for this Bill to restructure Irish Steel's finances.
Up to Ireland's Accession to the EEC, Irish Steel operated with marginal profits, behind a protective tariff wall. Their production capacity at that stage was small, only about 150,000 tonnes and was aimed at supplying the needs of the Irish market only. Exports took place from time to time but the quantity exported was very small and was directed almost entirely at the UK market.
By the mid-seventies, it had become clear that the company could no longer maintain their traditional operation. The dismantling of the protective tariffs meant that European producers, some of whom are amongst the world's most efficient, now had free access to the Irish market. In these circumstances, Irish Steel's plant was not modern or efficient enough to compete. The company commissioned a Canadian engineering firm to draw up a plan for the physical restructuring of the plant. Work on implementing this plan began in 1978.
The old plant was almost totally replaced, and production capacity was increased from 150,000 tonnes of crude steel to 345,000 tonnes, equivalent to about 300,000 tonnes of finished product. The new plant consists of an electric furnace, melting 114 tonnes of scrap to produce 90 tonnes of steel every two to three hours, a continuous casting machine, and a specially designed rolling mill which can produce bars which are round, angular or flanged in cross-section in dimensions from 12mm thickness to 120mm, and up to 70 metres long.
The project is now complete in all essentials, and its final cost is estimated to be £80 million. This is accounted for as £64 million for fixed assets and capitalised interest, and £16 million for additional working capital.
The actual cost of fixed assets and pre-production expenses, at £64 million, is more than double the original estimate, which the Government approved in February, 1977. The resulting level of debt is an additional handicap on the company in their efforts to attain viability.
The reasons for the cost increases are many, the principal ones being the fact that the orginal estimate was based on a general design concept rather than of firm tenders; and the need, after work began, to modify extensively the design in the light of experience.
The level of cost increase is a serious cause for concern, but the fact remains that the extra costs have already been incurred and the problem now is to deal with their consequences.
The cost of the project is itself only one of the costs incurred by Irish Steel, although it is the major one. In addition, the company have suffered losses since 1974 due, firstly, to the obsolescence of the old plant, secondly, because it was necessary to suspend production for 18 months during the installation of the new equipment and, finally, since July 1981 losses have occurred while running in the new plant and attempting to break into export markets. Accumulated losses at 30 June 1982 are about £49 million, of which £22.8 million was incurred in the past year.
The combined effects of the project cost and losses can be seen from the financial state of the company. At 30 June 1982, the unaudited balance sheet of the company shows assets of about £69 million, financed by share capital of £25 million; grant capital of £29 million; loans of £64 million; less accumulated losses of £49 million.
Irish Steel will need a further £11 million in loans to enable them to operate up to the end of the year. Their ability to obtain this finance is heavily dependent on the enactment of legislation to enable the Minister for Industry and Energy to guarantee further loans. As the existing guaranteeing limit of £60 million has been reached, the limit must be raised.
Increasing the amount of borrowing which may be guaranteed will not of itself solve the company's problems. The burden of debt is too large to allow the company to make profits, and fundamental financial restructuring is clearly necessary. The full extent and form of restructuring required is not yet clear due to a number of factors, market prospects being the major one.
The world steel markets are very depressed at present, and Europe is in a particularly bad situation. It is estimated that the over-capacity for steel production in Europe is now 30 million tonnes per year. This situation arose partly because the steel industry has never recovered from the oil crisis of 1974-75 — and indeed the latter one in 1979 — and partly because of increasing competition from countries such as Japan, Korea and Brazil, who have newer, more modern steel plants, and often have cheaper labour and energy.
It may seem strange that Irish Steel increased their production capacity at a time when great overcapacity already existed. This apparent anomaly arose because the type of plant chosen by the company, while it is the most modern available, cannot operate viably below the size chosen by Irish Steel. This minimum size was over twice the size of the company's old plant.
At this point I would like to comment on the level of competition from countries outside the EEC. These imports are causing great problems in Europe, particularly this year. Indeed, Irish Steel themselves suffered from the importation into Ireland of 11,000 tonnes of reinforcing bars from Argentina in the early part of this year. The reason for the present glut of third country imports is that the world steel market is so depressed that producers try to achieve sales at almost any price, while the European producers, in an attempt to ensure their survival, raised their prices on 1 January 1982, thus giving the third country producers greater scope for exporting to the EEC.
The EEC's trade relationships are complex and delicate. It is not possible to prevent imports without jeopardising exports, and since the EEC is a net exporter of about 13 million tonnes a year, it is obviously necessary to be careful in this area. The same reasoning applies in Ireland's case, as Irish Steel will need to export some 70 per cent of the 250,000 tonnes they will produce when running at full capacity.
The only way to counteract imports, therefore, is within the framework of existing agreements. These allow anti-dumping duties, countervailing duties and other measures, provided evidence exists that the imports are competing unfairly with European steel. It is also possible when renegotiating agreements with the EEC's main trading partners to restrict the quantity of imports. In the case of the Argentinian imports I have mentioned, an anti-dumping complaint is being investigated by the Commission, while on the broader question, the Minister for Industry and Energy will be pressing to make the EEC's trade agreements for steel more restrictive when they come to be reviewed.
In addition to the problem of competing imports, European producers also have problems caused by internal competition. In an effort to streamline the industry, control destructive competition, and improve Europe's competitive position, the European Commission prepared a plan in the late seventies called the "Davignon Plan". The main measures currently in operation under this plan are restrictions on investment in steel; restrictions on State aid to steel; restrictions on steel production; measures to raise prices and control competition; aids for redundancy, short-time working and early retirement; loans to help industries which employ redundant steel workers; and loans to help steel undertakings to increase their efficiency and reduce their production capacity.
Our concern in discussions on these measures has been to ensure that Irish Steel's prospects of viability are not damaged, particularly by restrictions on State aid and restrictions on production. As the company's development plan was approved by the Commission, it would now clearly be unfair if Commission measures rendered it unprofitable. I am now happen that the likelihood of this is remote.
While steel is not our most important industry, representing less than 0.2 per cent of Community production, it is of vital importance for most other members of the EEC. For this reason, it is essential that all countries strictly adhere to the Commission rules. Otherwise market chaos would ensue, with the effect of causing severe distress throughout the Community. One important consequence of this for Ireland is that the State aids code must be observed. This lays down that all intended aids for steel must be notified to the Commission by 30 September 1982, for prior approval and that aids cannot be paid after 31 December 1985.
This means that the Government must decide by 30 September on the funding requirements of the company for the foreseeable future, as no further aids will be allowed. A firm of consultants, jointly appointed by me and by the Commission, are currently studying this question, and they will report by the beginning of September.
It will be clear to the Seanad from what I have already said that the prospects for Irish Steel are difficult in the extreme. The company must achieve levels of exports far above any previous achievement, at a time when the European and world markets are at their most depressed level for many years, and at a time when established producers are being forced to reduce their production capacity as demand will not match supply for some years to come.
It gives me no pleasure to paint such a gloomy picture, but I consider it my responsibility not to mislead this House with a falsely encouraging picture. There are encouraging aspects in this situation, however, which I will turn to now.
Irish Steel now have one of the most modern plants of its size in the world. They have a great advantage over their competitors in being able to produce well over 100 products, although for technical reasons it is envisaged that no more than 84 will be produced. The result of this is that it is the only plant of its size which can offer merchants such a complete range of products, while its flexible design enables it to change its production to suit market trends. In general, it is fair to say that a small, efficient and flexible producer has a special advantage in the market, however depressed it may be. This is borne out by the fact that the only type of plant now making profits in Europe is the so-called "mini-mill", which is the type of plant used by Irish Steel. Taking all these factors into account, Irish Steel's prospects, in spite of the difficulties which can be expected, should be reasonably good with a proper approach to sales management and cost control.
An example of the difficulties which can arise is now taking place. Due to poor sales in their first year of operating the new plant, when sales were 41,500 tonnes against a projected 110,000 tonnes, it has proved necessary to introduce a three-day working week from 5 July. This measure affects about 500 of the 637 workers at the factory, and it is to be hoped that the situation will soon improve enough to allow a resumption of normal working.
On the question of management, the company have been keenly aware of the need for staff of the highest calibre. Since the beginning of the project, a total of 20 new management personnel have been recruited, including a new sales manager with considerable international experience, and a new chief executive.
Irish Steel are under no misapprehension of the difficulties facing them. They are facing a very severe test in the market place, while at the same time coping with severe financial problems due to their high burden of debt. The company will need constantly to increase their borrowings unless a major financial restructuring is carried out. Financial restructuring in this case inevitably involves State aid and, as I have already stated, no aid can be paid without the prior approval of the Commission, and the Commission will not approve such aid unless the basic viability of the company is established.
The only other provision in this Bill is a minor amendment to provide that the company should comply with directives about remuneration and conditions of employment issued from time to time by the Minister for Industry and Energy, with the consent of the Minister for the Public Service.
To conclude, I would hope that, in spite of the many difficulties now facing Irish Steel, the future of the company can be assured.
I am confident that the Bill will commend itself to the Seanad and I recommend the Bill for its approval.