Olivia Mitchell

Question:

370 Ms O. Mitchell asked the Minister for Transport the cost, as given in the Atkins report, of adjusting the backfill in the port tunnel in order to give a 4.9 m clearance for trucks. [3829/05]

View answer

Written answers

The cost of options outlined in the Atkins report to achieve a 4.9 m operational height ranged from €59 million to €111 million. The full Atkins report is available on my Department's website at www.transport.ie.