Water and Sewerage Schemes.

Dáil Éireann Debate, Tuesday - 9 October 2007

Tuesday, 9 October 2007

Questions (414, 415)

Joanna Tuffy

Question:

504 Deputy Joanna Tuffy asked the Minister for the Environment, Heritage and Local Government the position with regard to the proposed new sewerage scheme for Courtmacsherry and Timoleague, County Cork; when he expects work to commence; and if he will make a statement on the matter. [22337/07]

View answer

Written answers

The Courtmacsherry and Timoleague sewerage scheme is included in my Department's Water Services Investment Programme 2007-2009 as a scheme to begin construction in 2009.

My Department is awaiting the submission of a revised Preliminary Report for the scheme by Cork County Council. Following approval of the Preliminary Report the Council will be in a position to draw up Contract Documents.

Joanna Tuffy

Question:

505 Deputy Joanna Tuffy asked the Minister for the Environment, Heritage and Local Government the status with regard to the proposed new sewerage scheme at Summercove, Kinsale, County Cork; when he expects work to commence; and if he will make a statement on the matter. [22338/07]

View answer

The Kinsale Sewerage Scheme has been approved for construction under my Department's Water Services Investment Programme 2007-2009 at a cost of €20 million.

I understand that work has already begun on the upgrading of the collection system. Cork County Council's Tender Documents for the new wastewater treatment plant are being examined in my Department and are being dealt with as quickly as possible.