Skip to main content
Normal View

Electricity Transmission Network

Dáil Éireann Debate, Wednesday - 19 October 2011

Wednesday, 19 October 2011

Questions (84, 85, 86, 87, 88)

Sean Conlan

Question:

84 Deputy Seán Conlan asked the Minister for Communications, Energy and Natural Resources his view on EirGrid’s assertion that the savings from the proposed North-South interconnector are slightly lower but very similar to the savings from the east-west interconnector, in view of the fact that fuel mix in the United Kingdom is different, that there exists tighter correlation of wind generation in Northern Ireland and Ireland compared to Ireland and the United Kingdom, and in view of the interconnection of the United Kingdom with the Netherlands and France as well as limits on the Moyle interconnector; and if he will make a statement on the matter. [30356/11]

View answer

Written answers

I am not aware of EirGrid making any assertion that the savings from the proposed North-South interconnector are slightly lower but very similar to the savings from the East-West interconnector.

A summary of the net savings associated with the East-West interconnector are included in the 2009 "Interconnection Economic Feasibility Report" published by EirGrid. This report examines the economic feasibility of interconnection between the island of Ireland (the All Island (AI) system) and Great Britain or France and includes a range of cost savings associated with additional levels of interconnection capacity. In the case of the East-West interconnector, base case net savings in the range of €42m to €85m per annum are forecast. These net benefit figures comprise of production cost savings (fuel and CO2) and capacity benefits (linked to generation adequacy and capacity payments) and is net of the annualised capital costs of the East-West Interconnector.

EirGrid is currently carrying out a re-evaluation of the North-South interconnection project. As part of this review, a study is under way to quantify the savings associated with the North-South interconnector. Initial results from this study, which will be published shortly, indicate cost savings in the range €20m to €30m per annum. While the economic feasibility studies for each of the interconnectors has been undertaken separately, each study was based on the assumption that both interconnectors were in place. This ensures that the full savings benefit that can be realised to consumers through these strategically critical electricity infrastructure investments is quantified.

Together, both interconnectors will play a significant role in ensuring that Ireland will meet its 40 percent renewable energy target by 2020. The benefits include, in the case of the North-South interconnector, support for the efficient operation of the Single Electricity Market and the related strengthening of the all Island transmission network while the East-West interconnector will provide additional and significant reduction in potential levels of wind curtailment. The latter is in part related to less correlated wind profiles between the All-Island system and neighbouring systems. These differences are fully reflected in both studies.

Sean Conlan

Question:

85 Deputy Seán Conlan asked the Minister for Communications, Energy and Natural Resources the discount rate used to work out the feasibility of Eirgrid projects; and if he will make a statement on the matter. [30357/11]

View answer

Sean Conlan

Question:

86 Deputy Seán Conlan asked the Minister for Communications, Energy and Natural Resources the time horizon Eirgrid uses in assessing feasibility; and if he will make a statement on the matter. [30358/11]

View answer

Sean Conlan

Question:

87 Deputy Seán Conlan asked the Minister for Communications, Energy and Natural Resources if 110 kV interconnector lines will be upgraded; if so, the voltage of the upgraded lines; if they will be upgraded, the reason they were not considered in the feasibility studies carried out in the early 2000s; and if he will make a statement on the matter. [30420/11]

View answer

I propose to take Questions Nos. 85 to 87, inclusive, together.

The discount rate used by EirGrid for investment appraisals and feasibility studies has been informed by and is consistent with regulatory determinations. The Commission for Energy Regulation recently determined the regulated real pre-tax Weighted Average Cost of Capital as 5.95%.

The time horizon used by EirGrid for investment appraisals and feasibility studies has been informed by and is consistent with regulatory determinations. In this regard, the Commission for Energy Regulation has recently determined that the Regulatory Asset Base would continue to be depreciated over 50 years.

The planning, development and routing of transmission line infrastructure is a matter for EirGrid, which is the State owned body responsible for the electricity transmission system. I have no statutory function regarding the planning and construction of energy networks.

However, I can confirm that there are two existing 110 kV cross border circuits connecting between the Republic of Ireland and Northern Ireland. One circuit connects Letterkenny in County Donegal to Strabane in County Tyrone; the other connects Corraclassy in County Cavan to Enniskillen in County Fermanagh. The 110kV network on both sides of the border, in these border counties, is relatively weak and the two 110kV cross border circuits were installed in order to provide emergency local support in one jurisdiction in the event of a problem in the other.

They operate as standby circuits and do not carry power under normal circumstances.

The quantity of electrical power that can be transferred via these existing cross border 110 kV circuits is constrained not only by the power carrying capacity of the circuits themselves but also by the weak 110 kV network into which they connect, on both sides of the border.

To increase the power transfer capacity of the existing cross border 110 kV circuits would therefore require an upgrade of not just the circuits themselves but also an extensive and deep upgrade of the 110 kV networks in both jurisdictions. Implementing such an upgrade by increasing the voltage rating of the existing circuits up to, say 275 kV, would require a re-build of the networks on both sides of the border. This would require such prolonged outages in the areas concerned that, even if such a rebuild of the network was feasible from an environmental and public planning perspective, it cannot be considered as a practical proposition. As a consequence it was not considered as an option in the joint feasibility studies carried out by EirGrid and Northern Ireland Electricity during the years 2001-2005.

The 2001-2005 feasibility studies were recently reviewed by EirGrid as part of its project re-evaluation process. The findings of this review, published by EirGrid in its Preliminary Re-evaluation Report of May 2011, confirmed that the most appropriate option for achieving the required increase in the capacity of North South Interconnection remains the installation of a new high capacity 400 kV circuit connecting between the existing Woodland Substation in County Meath and a new substation at Turleenan in County Tyrone and routed via the vicinity of Kingscourt in County Cavan.

In July 2011 the Minister appointed an expert independent international commission to investigate the case for undergrounding all, or part of, this proposed 400 kV circuit. The Commission is expected to report its findings in the near future.

Sean Conlan

Question:

88 Deputy Seán Conlan asked the Minister for Communications, Energy and Natural Resources the reason the Moyle connector was run below maximum capacity; if maximising it would decrease the need for the north-south interconnector; and if he will make a statement on the matter. [30421/11]

View answer

The planning, development and routing of transmission line infrastructure are a matter for EirGrid, which is the State owned body responsible for the electricity transmission system. I have no statutory function regarding the planning and construction of energy networks. In particular, I have no function regarding the Moyle electricity connector which connects Northern Ireland and Scotland.

The European Commission is giving particular strategic priority to strengthening electricity interconnection across Europe. The enhancement of regional co-operation, including improved electricity interconnectivity between Member States, is a key objective of the EU Energy Third Package.

The Government fully endorses the strategic national importance of investing in Ireland's electricity transmission infrastructure.

In that context the Meath-Tyrone 400KV Interconnector is a key strategic project for the economies and consumers both North and South. It is also critical to ensuring energy supply adequacy on the island of Ireland. It will play a significant role in ensuring that Ireland will meet its 40 percent renewable energy target by 2020. The benefits include support for the efficient operation of the Single Electricity Market and the related strengthening of the all Island transmission network.

Investment in the development and maintenance of Ireland's electricity network infrastructure is of fundamental strategic importance for the economy. Secure and reliable energy supply is a prerequisite for inward investment, for indigenous enterprise, and for all consumers.

Ireland has achieved a reliable and modern electricity infrastructure over the last decade. The building of these modern and reliable energy network systems was achieved by extensive and well executed investment by the State owned companies, ESB and EirGrid. The networks must be maintained and enhanced as necessary to ensure that Ireland has an energy infrastructure which is fully fit for purpose. Investment in strategic energy infrastructure is also a key priority for the European Union.

The Government fully endorses the strategic national importance of investing in Ireland's electricity transmission infrastructure. Delivery by EirGrid of its national grid development strategy "GRID 25" is critical to economic recovery, regional development, security of supply, competitiveness and the achievement of Ireland's renewable electricity targets.

Top
Share