Skip to main content
Normal View

Regeneration Projects Status

Dáil Éireann Debate, Wednesday - 3 October 2012

Wednesday, 3 October 2012

Questions (148)

Dessie Ellis

Question:

148. Deputy Dessie Ellis asked the Minister for the Environment; Community and Local Government if he will give a timeline for the demolition of the remaining units at a location (details supplied) in Dublin 9. [42089/12]

View answer

Written answers

My Department recently issued approval to Ballymun Regeneration Limited (BRL) to proceed to tender for Demolition Contract 8, which provides for the demolition of the flat complexes on Shangan Road and Sillogue Road. I understand from BRL that tenders for these works are under examination and it anticipates that the demolition of these units will be completed towards the middle of next year.

The detonating and subsequent demolition of the Balbutcher flat complex and Plunkett Tower must await the completion of the new housing projects currently under construction. Proposals for the demolition of these units are awaited from BRL.

Top