Skip to main content
Normal View

Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 28 May 2013

Tuesday, 28 May 2013

Questions (108)

John Halligan

Question:

108. Deputy John Halligan asked the Minister for Education and Skills if he will indicate when a school (details supplied) in County Dublin will get the funds for upgrading and refurbishment for which it has been waiting for for 14 years; and if he will make a statement on the matter. [25473/13]

View answer

Written answers

The major building project referred to by the Deputy is at an advanced stage of architectural planning. Stage 2b of the project which includes Planning Permission, Fire Certification, Disability Access Certification (DAC) and the preparation of tender documents has been approved. The project was recently authorised to pre-qualify for contractors which will complete Stage 2b. The project is scheduled on the five year school building programme to go to construction in 2015/16.

Top
Share