Skip to main content
Normal View

Schools Building Projects Status

Dáil Éireann Debate, Wednesday - 20 November 2013

Wednesday, 20 November 2013

Questions (91)

John Paul Phelan

Question:

91. Deputy John Paul Phelan asked the Minister for Education and Skills the position regarding the construction of a school extension (details supplied) in County Waterford ; when he expects the project to be completed; and if he will make a statement on the matter. [49695/13]

View answer

Written answers

Responsibility for the delivery of an extension to the school referred to by the Deputy has been devolved to Kilkenny & Carlow Education and Training Board (ETB).

I understand the Design Team appointed by the ETB are currently completing the Stage 2a Submission (Developed Sketch Design) and, when complete, consideration will be given to allowing the ETB proceed to Stage 2b - Detailed Design, which involves obtaining planning permission, fire certificate and disability access certificate and the completion of tender documents.

Top
Share