Flood Risk Assessments

Dáil Éireann Debate, Wednesday - 22 January 2014

Wednesday, 22 January 2014

Questions (19)

Denis Naughten

Question:

19. Deputy Denis Naughten asked the Minister for Public Expenditure and Reform the steps being taken to address flood risks within the Shannon basin; and if he will make a statement on the matter. [2577/14]

View answer

Written answers

The core strategy for addressing flood risk in the Shannon Basin is the River Shannon Catchment Flood Risk Assessment & Management Study. The CFRAM Study is being conducted by Jacobs Engineering on behalf of the OPW and I am advised that good progress is being made on the project. A total of 66 areas along the Shannon, have been designated as Areas for Further Assessment under the Study. The output of this important project will be an integrated plan of specific measures to address, in a comprehensive and sustainable way, the significant flood risk factors in the Shannon basin, including the Callows area.

As the Deputy is aware, operational control of water flows and levels on the Shannon is the responsibility of both the ESB and Waterways Ireland. In order to address ongoing concerns that the existing water level control regime may be a contributory factor in early Summer flooding in the Callows, the OPW facilitated discussions between these principal operating stakeholders toward agreeing a new interim control regime on the regulation of levels. Under this interim regime the ESB agreed to a trial lowering of the Spring/early Summer target levels in Lough Ree to reduce somewhat the risk of summer flooding, particularly in the Shannon Callows area. This trial commenced in Summer 2013 and will remain in place until the publication of the Shannon CFRAM Plan.

On foot of discussions between my office and the IFA, and with the cooperation of both the ESB and Waterways Ireland, a water level monitoring exercise is being carried out as part of the CFRAM process which will allow for analysis of water flows and levels at key points around the Lough Ree and Callows areas. Data from this exercise has been collated and the results have been forwarded to the CFRAM consultants. This data will feed into the overall Shannon CFRAM study and the interim data will be published on the website, www.shannoncframstudy.ie. The OPW will continue to review these developments on a regular basis in consultation with the ESB and Waterways Ireland.