Flood Prevention Measures

Dáil Éireann Debate, Wednesday - 22 January 2014

Wednesday, 22 January 2014

Questions (85)

Terence Flanagan

Question:

85. Deputy Terence Flanagan asked the Minister for Public Expenditure and Reform the number of applications that have been made by Dublin City Council and Fingal County Council for funding towards flood alleviation and prevention measures; and if he will make a statement on the matter. [3007/14]

View answer

Written answers

Details of the applications approved, refused or under consideration for funding under the Minor Flood Mitigation Works and Coastal Protection Scheme submitted by Dublin City Council and Fingal County Council from 2009 to date are outlined in the following tables.

Dublin City Council Minor Flood Mitigation Works & Coastal Protection Scheme Funding Applications Approved

2011 Project Location

Amount of Funding Approved

Date of Approval

Dodder Estuary, Fitzwilliam Quay

€400,000

25/03/11 & 06/10/11

Raheny Village & Harmonstown Road

€135,000

29/11/11

2012 Project Location

Amount of Funding Approved

Date of Approval

Carrickfoyle Tce, Millbrook Tce, Lady's Lane, Kilmainham

€225,000

15/05/12

Funding Applications Not approved

2009 Project Location

Reasons for Non-approval

Wad River

Funding provided by OPW to undertake a number of studies

2010 Project Location

Reasons for Non-approval

Glendhu Park, Ashtown

Pluvial related – outside scope of Minor Works Scheme

Camlough, Dingle Road & Drumcliffe Drive, Cabra

Pluvial related – outside scope of Minor Works Scheme

Ballygall Crescent, Fairways Ave & Griffith Road, Finglas

Pluvial related – outside scope of Minor Works Scheme

Fingal County Council Minor Flood Mitigation Works & Coastal Protection Scheme

Applications Approved

2011 Project Location

Amount of Funding Approved

Date of Approval

Aspen, Swords

€54,000

02/08/11

Rolestown East

€153,000

02/08/11

2013 Project Location

Amount of Funding Approved

Date of Approval

Portrane/Rush (Coastal)

€57,800

25/02/13

The Grange, Malahide

€93,600

13/05/13

Applications Not Approved

2009 Project Location

Reasons for Non-approval

Greenfield Road/Strand Road, Sutton (coastal)

Did not meet Minor Works Scheme criteria- estimated cost is over the Scheme limit of €500,000

Rush to Portrane- Coastal Monitoring Programme

The Council were asked in 2012 to resubmit under revised coastal criteria

Strand Road, Baldoyle to Portmarnock (coastal)

Did not meet Minor Works Scheme criteria- estimated cost is over the Scheme limit of €500,000

2010 Project Location

Reasons for Non-approval

Bloody Stream, Howth

Did not meet the criteria of the Minor Works Scheme-Benefit Cost Ratio below the required minimum

Eircom Telephone Exchange, The Grange, Malahide

Did not meet the criteria of the Minor Works Scheme-Benefit Cost Ratio below the required minimum

Spout Lane, Lusk

Did not meet the criteria of the Minor Works Scheme-Benefit Cost Ratio below the required minimum

Strawberry Beds

Did not meet the criteria of the Minor Works Scheme-Benefit Cost Ratio below the required minimum

Portmarnock Road Roundabout (coastal)

The Council were asked in 2012 to resubmit under revised coastal criteria

Golf Links Road, Portmarnock (coastal)

The Council were asked in 2012 to resubmit under revised coastal criteria

2011 Project Location

Reasons for Non-approval

Burrow Road Beach (coastal)

Did not meet the criteria of the Minor Works Scheme-Benefit Cost Ratio below the required minimum

The Council were asked in 2012 to resubmit under revised coastal criteria

Strand Road, Portmarnock (coastal)

Did not meet Minor Works Scheme criteria, estimated cost is over the Scheme limit of €500,000

The Council were asked in 2012 to resubmit under revised coastal criteria

Applications under Consideration

2013 Project Location

R127 Skerries/Balbriggan Regional Road (coastal)

Malahide Town Centre (coastal) (Awaiting further details- to be submitted by the Council)