Skip to main content
Normal View

Wednesday, 29 Jan 2014

Written Answers Nos. 119-125

Building Regulations Compliance

Questions (119)

Kevin Humphreys

Question:

119. Deputy Kevin Humphreys asked the Minister for the Environment, Community and Local Government in respect of capital building projects under the remit of his Department and the building programmes planned for 2014, if he will outline the impact the new building control regulations 2013, that come into effect on 1 March, will have on the costs of each specific project; if he will list the projects under way; the extra costs that will be incurred on each project due to increased professional fees and increased supervision; and if he will make a statement on the matter. [4365/14]

View answer

Written answers

The new Building Control Amendment Regulations which come into operation on 1 March 2014 will greatly strengthen the arrangements currently in place for the control of building activity by requiring greater accountability in relation to compliance with Building Regulations in the form of statutory certification of design and construction, lodgement of compliance documentation, mandatory inspections during construction and validation and registration of certificates.

An extensive public consultation process was undertaken in 2012 to inform the development of the revised regulations. Comprehensive consultation documents were published including Strengthening the Building Control System - A document to inform public consultation on Draft Building Control (Amendment) Regulations 2012 which sets out the context in which the reforms will operate and the regulatory impact of these for building owners (including public contracting authorities) and industry stakeholders. In summary terms, it can be said that the arrangements being put in place for the control of building activity may result in additional design, certification and, possibly, insurance costs which must ultimately be borne by the building owner/contracting authority. Such additional costs would be justified by the enhanced quality and standard of design and construction of the building project concerned in light of several notable instances of non-compliant buildings which failed to meet minimum building standards. It is anticipated that the statutory inspection process will reduce the incidences of defective works on site and the resultant associated costs of carrying out remedial works will reduce accordingly.

The new statutory requirements apply to projects for which commencement notices are submitted on and after 1 March 2014. In this regard public construction projects which are currently underway or which are validly commenced prior to I March 2014 will be unaffected by the new requirements. Projects for which tender documents are currently being produced will be advertised having regard to the new statutory requirements, and the contract price will be determined by competitive tender in line with normal arrangements. Projects for which contractual arrangements have previously been entered into but which have not yet commenced will now have to reflect the additional requirements of the new regulations. The suite of public works contracts and conditions of engagement as set out in the Capital Works Management Framework provides context for addressing the additional statutory requirements and the associated costs. As part of the competitive process for each project, the standard conditions of engagement require consultants to submit rates for time charges and these tendered rates are evaluated before appointment. The submitted rates will provide the basis for reimbursement for any additional services required from the consultants arising from the requirements of the new regulations. The additional cost arising for each project will depend on the particular specifics of that project.

My Department’s capital programmes include responsibility for Housing, Environmental Protection, Fire Services, Libraries and other capital projects implemented primarily by local authorities. Any additional costs for projects which are now subject to contract but which have not yet commenced will, in the first instance, be a matter for the contracting authority . Funding provided by my Department for capital works is subject to detailed scrutiny at critical stages, in line with the Capital Appraisal Guidelines and value for money principles.

Waste Management

Questions (120)

Brian Stanley

Question:

120. Deputy Brian Stanley asked the Minister for the Environment, Community and Local Government to identify the person who commissioned the reports by a company (details supplied) on local waste management plans; and the amount that he or she was paid. [4381/14]

View answer

Written answers

The preparation and adoption of a waste management plan is the statutory responsibility of the local authority or authorities concerned. Under section 60(3) of the 1996 Act, I am precluded from exercising any power or control in relation to the performance by a local authority, in particular circumstances, of a statutory function vested in it.

Water Meters Installation

Questions (121, 132)

Kevin Humphreys

Question:

121. Deputy Kevin Humphreys asked the Minister for the Environment, Community and Local Government if his Department commissioned a study on the technical aspects governing metering of multi-unit developments for Irish Water; if he will publish this report or provide a copy of it to this Deputy; the person from whom the report was commissioned; the amount it cost; and if he will make a statement on the matter. [4382/14]

View answer

Róisín Shortall

Question:

132. Deputy Róisín Shortall asked the Minister for the Environment, Community and Local Government further to Parliamentary Question No. 451 of 22 January 2014, if he will address the specific questions raised; namely, if his Department will provide a projected timeline for the installation of water meters to the 300,000 homes that have not been included in the initial roll-out of metering; if it is the intention of Irish Water and his Department that these homes will be installed with meters in the foreseeable future; if two homes sharing a single connection will be treated differently from an apartment block; and the reason this supply cannot be split as part of the meter installation programme; if he will provide an update on the deliberations of the Commission for Energy Regulation regarding charges; and if he will make a statement on the matter. [4498/14]

View answer

Written answers

I propose to take Questions Nos. 121 and 132 together.

The Programme for Government sets out a commitment to the introduction of water charges based on usage above a free allowance The Government considers that charging based on usage is the fairest way to charge for water and it has therefore decided that water meters should be installed in households connected to public water supplies. The Water Services Act 2013 provides for the establishment of Irish Water as an independent subsidiary within the Bord Gáis Éireann Group and assigns the necessary powers to allow Irish Water to undertake th e metering programme. The installation programme commenced in August 2013 and will be implemented nationally as quickly as possible.

Up to 300,000 households may not be metered in the initial metering programme due to either the high cost or the technical difficulty of doing so. As the Government’s objective is to ensure as many households as possible are metered, my Department provided funding of €570,000 in 2013 to fund the cost of a study by Irish Water on possible approaches to metering properties that will not be included in the current metering programme, including apartments and properties with shared service connections. The study involved the following: desktop studies of data on the properties to be covered in the phase 2 programme including the age, configuration and distribution of the properties; field surveys; pilot studies to investigate design solutions and technological solutions; and sample meter installations in apartment blocks to validate design solutions.

This study has very recently been submitted to my Department for consideration and, as such, any proposals for the metering of these properties would need to be considered by the Government in the first instance. The report will be published as soon as possible following its consideration. The Water Services Acts 2013 provide that the Commission for Energy Regulation (CER) will be responsible for the independent economic regulation of Irish Water.  In particular, the CER will be responsible for approving the water charges plans prepared by Irish Water, and for approving codes of practice to be prepared by Irish Water. The primary role of the Regulator will be to protect the interests of customers and to ensure a consistent and appropriate level of service is provided to them.  In discharging its functions, the CER proposes to undertake a public consultation on the approach to the design of domestic water tariffs during 2014. This will include the approach to charges for both metered and unmetered properties.

Irish Water Expenditure

Questions (122)

Kevin Humphreys

Question:

122. Deputy Kevin Humphreys asked the Minister for the Environment, Community and Local Government if he will provide a breakdown of all expenditure in his Department for 2013 associated with the establishment of Irish Water, including any sums spent on external advisers; the projected spend in 2014; the way in which this will be spent; and if he will make a statement on the matter. [4383/14]

View answer

Written answers

My Departmental costs and Local Authority costs relating to the Water Sector Reform Programme have been met from the Departmental Vote. These costs amounted to €15.5m in 2013. The majority of this expenditure related to the domestic metering programme (€7.7m) and the local authority staffing costs of the Water Services Transition Office (€5.7m), which was put in place to ensure appropriate arrangements for engagement with the local authority sector during the reform process. In addition, Departmental costs which included the staffing of the Water Sector reform Project Management Office in my Department, amounted to some €1.3m in 2013.

The balance of the costs incurred in 2013 includes €0.76m paid to the Commission for Energy Regulation in respect of their expanded functions in becoming the independent economic regulator for the public water sector and €55,000 paid to the Economic & Social Research Institute in respect of providing research and advice on affordability issues associated with the introduction of domestic water charges.

It is estimated that some €2m will be spent on my Department’s programme management and the Transition Office during 2014. It is also expected that some €5m will be re-couped to local authorities in connection with road-opening licence work associated with the national domestic metering programme. In 2014, Irish Water, which now has statutory responsibility for water services, will receive €240m in equity from the Minister for Finance and some €490m from the Local Government Fund but no other funding from the Department’s Vote for establishment or other costs. Irish Water is currently preparing a Capital Investment Plan for 2014 – 2016 that will provide for the transition of projects previously included in my Department’s 2010 - 2013 Water Services Investment Programme.

Local Authority Funding

Questions (123)

Kevin Humphreys

Question:

123. Deputy Kevin Humphreys asked the Minister for the Environment, Community and Local Government if his Department gave consent for the expenditure of €12 million on a district heating scheme in the Dublin 4 area associated with the Poolbeg incinerator; the amount his Department provided for same; the person who signed off on the expenditure; if external consultants were commissioned for this work; if he will provide a copy of all documents in his Department related to this specific project; and if he will make a statement on the matter. [4384/14]

View answer

Written answers

Questions regarding the development of a district heating scheme in the Dublin 4 area are a matter for Dublin City Council. My Department has not provided funding to Dublin City Council in respect of a district heating scheme.

Irish Water Appointments

Questions (124, 125)

Brian Stanley

Question:

124. Deputy Brian Stanley asked the Minister for the Environment, Community and Local Government the methods that were used to select and appoint members of the board of Irish Water; and the number of persons that applied for the position. [4386/14]

View answer

Brian Stanley

Question:

125. Deputy Brian Stanley asked the Minister for the Environment, Community and Local Government the current corporate relationship between Irish Water and Bord Gáis. [4387/14]

View answer

Written answers

I propose to take Question Nos. 124 and 125 together.

The Water Services Act 2013 provided for the establishment of Irish Water as a subsidiary of Bord Gáis Éireann (BGE) and that the new company should be formed and registered under the Companies Acts. The Memorandum and Articles of Association, which were adopted by Irish Water on its incorporation in July 2013, provide that the appointment of directors to the Board of Irish Water is the responsibility of the Board of BGE with the approval of the Minister for the Environment, Community and Local Government and the Minister for Communications, Energy and Natural Resources. Twelve directors have been appointed to the Board of Irish Water by BGE and these appointments were approved in advance by me, as Minister, and by my colleague, Minister Pat Rabbitte. The persons appointed by BGE have a broad range of relevant expertise, knowledge and experience which will be critically important in guiding Irish Water in its challenging start-up phase.

Top
Share