Primary Care Centres Provision

Dáil Éireann Debate, Wednesday - 9 April 2014

Wednesday, 9 April 2014

Questions (184)

John Deasy

Question:

184. Deputy John Deasy asked the Minister for Health the position regarding the proposed primary care centre for Dungarvan, County Waterford; if progress has been made in securing a public private partnership, PPP, partner; and if he will make a statement on the matter. [17009/14]

View answer

Written answers

Considerable progress has been made in developing the primary care centre PPP project. The HSE lodged the planning application for the Dungarvan primary care centre in November 2013 and has been advised that planning has been approved. Details are available on the local authority website.

The National Development Finance Agency (NDFA) published a Prior Indicative Notice (PIN) / Pre-qualification Questionnaire in the OJEU on 19 December 2013. Four submissions were received by the closing date which was 10 March 2014. Information can be located at the following web address - http://www.ndfa.ie/TenderCompetitions/PrimaryCareCentresPPPProgramme.htm

It is expected that 10-14 sites (indicative number 12 based on affordability) will be delivered as part of a single PPP contract with the remaining centres to be delivered by the HSE using other procurement means.