355. Deputy Billy Kelleher asked the Minister for Health to provide in tabular form the primary care centre projects announced on 17 July 2012; the current status of same; and if he will make a statement on the matter. [23312/16]

View answer

Written answers

The Programme for a Partnership Government sets out a clear vision for our health services which is community based and responsive and accessible to patients. Supporting infrastructure, procured through a combination of public and private investment, will facilitate the delivery of multi-disciplinary primary health care. However, while the Government's objective is to deliver a high quality, integrated and cost effective health care service the mechanism and timescale for delivery of primary care centres is dependent on a number of factors. Regardless of the delivery mechanism, all potential primary care infrastructure is subject to suitable locations being offered / provided / available, to successful planning processes and GP commitment to sharing accommodation and delivering health care services with HSE staff. In addition the operational lease mechanism is subject to market pressures such as the developers' access to adequate financing. Some of these factors are outside the control of the Health Service Executive. Delivery of primary care infrastructure is a dynamic process, constantly evolving to take account of changing circumstances including the feasibility of implementation. The current status of the projects is set out in the following table.

Primary Care Centres

July 2012 - 35 locations

PQ 23312/16 - answer 20/07/2016

Project Status

County

HSE Region

County

Location/PCT Name

Delivery Mechanism

Q2 2016 -30 June 2016

1

DML

Dublin

Rowlagh/North Clondalkin

Direct build

Stage 2a design team report now complete.  HSE finalising purchase agreement of site at Collinstown Park School. Purchase agreement is subject to planning permission being granted for the development.  

2

DML

Dublin

Crumlin/Drimnagh

Direct build

Planning not completed in timeframe for PPP.

3

DML

Dublin

Knocklyon/Rathfarnham

Direct build

Planning not completed in timeframe for PPP.

4

DML

Wicklow

Rathdrum

Operational Lease

Planning approved.  HSE has finalised layouts.  Construction due to commence end Sept 2016, with projected 13 month construction programme. Projected operational Q4 2017.

5

DML

Kildare

Kilcock

PPP

Construction underway - front entrance works and foundations.

6

DNE

Dublin

Coolock/Darndale

PPP

Construction underway - demolition works.

7

DNE

Dublin

Summerhill, north inner city Dublin

PPP

Construction underway - service diversion works.

8

DNE

Dublin

Balbriggan

Operational Lease

Construction underway and completion projected Q4 2016. Projected operational Q1 2017.

9

DNE

Dublin

Swords

Operational Lease

Preferred site sold. New advertisement required.

10

DNE

Louth

Drogheda north

Operational Lease

Developer re-engaged. Progressing to legal discussions.

11

DNE

Meath

Laytown and Bettystown

Operational Lease

Discussion underway with new owners.

12

DNE

Meath

Kells

Operational Lease

Operational Q1 2016

13

DNE

Monaghan

Carrickmacross

Nov 2014 advertisement for operational lease mechanism delivery.

No expressions of interest received.

Viable expression of interest received recently. Formal submissions awaited.

14

South

Carlow

Tullow/Rathvilly/Hacketstown

Direct build

Adjoining landowner has re-engaged with HSE. Options being reviewed.

15

South

Kilkenny

Kilkenny city

Nov 2014 advertisement for operational lease mechanism delivery - suitable for further consideration

Priced offer received. Letter of Intent issued.

16

South

Wexford

Wexford town

PPP

Construction underway - site works and demolition works.

17

South

Waterford

Dungarvan

PPP

Construction underway - preparing foundations.

18

South

Waterford

Waterford city

PPP

Construction underway - bulk excavation and piling works.

19

South

Cork

Cork city - Togher

Nov 2014 advertisement for operational lease mechanism delivery - suitable for further consideration

HSE reviewing stage 2 submissions. Stage 3 projected to proceed Q3 2016

20

South

Kerry

Tralee

Operational Lease

Re-advertised. Stage 2 review complete; stage 3 documentation being issued.

21

South

Tipperary

Carrick-on-Suir

PPP

Construction underway - site works and piling works.

22

South

Tipperary

Clonmel

Nov 2014 advertisement for operational lease mechanism delivery - suitable for further consideration

Stage 2 submissions being reviewed. Stage 3 projected to proceed in Q3 2016.

23

West

Tipperary

Thurles

Nov 2014 advertisement for operational lease mechanism delivery - suitable for further consideration

Letter of Intent issued 10/12/2015. Project progressing toward Agreement for Lease.

24

West

Limerick

Limerick city (Ballinacurra/Weston)

PPP

Construction underway - preparing foundations.

25

West

Clare

Ennis

Nov 2014 advertisement for operational lease mechanism delivery.

Re-advertisement to be considered.

26

West

Galway

Tuam

PPP

Construction underway - preparing foundations.

27

West

Galway

Gort

Nov 2014 advertisement for operational lease mechanism delivery.

Letter of Intent withdrawn 24/05/2016. Possible re-advertisement.

28

West

Roscommon

Boyle

PPP

Construction underway - preparing foundations.

29

West

Roscommon

Ballaghadereen

Nov 2014 advertisement for operational lease mechanism delivery - suitable for further consideration

Letter of Intent issued 27/10/2015. Progressing to Agreement for Lease.

30

West

Mayo

Westport

PPP

Construction underway - site works.

31

West

Mayo

Claremorris

PPP

Construction underway - preparing foundations.

32

West

Sligo

Ballymote

PPP

Construction underway - earthworks underway.

33

West

Donegal

Dungloe

Direct build

Extension to existing building. Absence of GP interest

34

West

Donegal

Donegal town

Operational Lease

Re-advertisement required.

In July 2012, Coolock and Darndale were announced as two separate locations but are being delivered as one location.