192. Deputy Brendan Smith asked the Minister for Arts, Heritage, Regional, Rural and Gaeltacht Affairs the status of the restoration of the Ulster Canal; the timeframe for the provision of a jetty by Waterways Ireland at Castle Saunderson, County Cavan; and if she will make a statement on the matter. [31330/16]

View answer

Written answers

The reopening of the 2.5km stretch of the Ulster Canal from Upper Lough Erne to the International Scout Centre at Castle Saunderson continues to progress. The project, which comprises three work phases, is being undertaken by Waterways Ireland. Phase 1, the site investigation work, and Phase 2, the dredging of the River Finn and removal of the dredging material, have been completed.

Waterways Ireland has informed me that it is currently completing the tender documentation for the final stage of works to provide navigation to Castle Saunderson. Subject to a successful tender and award process, it is proposed that works would start on site in Spring 2017 with an anticipated 18 month contract period.

I am also advised by Waterways Ireland that it continues to engage with Cavan County Council, which owns the property at Castle Saunderson, regarding the provision of a jetty at that location.