The major building project for the school to which the Deputy refers is at an advanced stage of architectural planning, Stage 2b – Detailed Design, which includes the applications for Planning Permission, Fire Cert and Disability Access Cert and the preparation of tender documents. All statutory approvals have been obtained.
The Design Team submitted the stage 2(b) report for the project in February 2018. Following examination of this report, it became apparent that the submission was incomplete. A revised stage 2(b) submission was requested from the school and it’s Design Team. This has recently been received and is currently under review in my Department. Upon review of the revised 2(b) submission, my Department will revert to the school with regard to the further progression of the project at that time.