Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 16 October 2018

Tuesday, 16 October 2018

Questions (258)

Bernard Durkan

Question:

258. Deputy Bernard J. Durkan asked the Minister for Education and Skills the extent to which the various schools affected by a contractor (details supplied) are progressing towards completion and available for the intake of pupils and students; and if he will make a statement on the matter. [42490/18]

View answer

Written answers

The following table sets out the current position in relation to the schools affected by the collapse of the building contractor referred to by the Deputy.

County

Roll No.

School

Type of project

Original planned Completion date

Revised planned Completion date

Dublin City

20047O

Gaelscoil Bharra, Cabra

New 8 classroom school

07/09/2017

School ready for occupation on 1/9/17, some ground works still to be completed

Laois

20270R

Portlaoise amalgamation, (St Paul's, Sacred Heart & Scoil Mhuire) Portlaoise Rd, Portlaoise, Co. Laois.

New Schools - 3 existing schools amalgamating into 2 new schools -

Two new 24 classroom schools with a combined GP Hall.

12/04/2016

Jnr School ready for occupation on 9/6/17 - Snr School ready for occupation on 29/8/17, some ground works still to be completed

Offaly

72560C

Tullamore College

Demolition of the existing single storey secondary school buildings and their replacement with a 7,076m2 part single part two storey school building to provide accommodation for 675 pupils

29/06/2016

School ready for occupation on 27/2/17, some ground works still to be completed

Wexford

12372G

New Ross Jnr & Snr Schools, Castlemoyle

2 new 18 classroom schools each with a 2 classroom ASD Unit

15/06/2016

Schools ready for occupation on 25/01/17, some snags/defects still to be rectified

Wicklow

70740M

Arklow Community College, Coolgreaney Rd, Arklow, Co. Wicklow.

New school to cater for 710 pupils

17/06/2016

School ready for occupation on 23/12/15, some ground works still to be completed

Cork

71050P

St Colman's College, Midleton, Co Cork

Extension of 5,640sqm including ASD Unit PE Hall to provide accommodation for

1000 pupils

10/02/2017

School should be ready for occupation Sept 2019

Cork

70990M

Coláiste an Chraoibhin, Fermoy, CO Cork

Extension of 3,845 sqm including ASD Unit PE Hall to provide accommodation for

850 pupils

15/12/2016

School should be ready for occupation Sept 2019

Kildare

70700A

Maynooth Post Primary School, Maynooth

Replacement school for

1000 pupils

18/05/2019

School should be ready for occupation June 2020

Kildare

76193Q

Maynooth Community College, Maynooth

New 1000 pupil

with a shared Sports Hall with Maynooth Post Primary School

18/05/2019

School should be ready for occupation June 2020

Carlow

70420R

Tyndall College

1000 pupil school

Q1/2018

School should be ready for occupation by end of 2018/early 2019.

Carlow

76514K

Carlow Institute of Further Education

1000 pupil school

Q1/2018

School should be ready for occupation by end of 2018/early 2019.

Meath

64410F

Eureka Secondary School, Kells

800 pupil school

Q1/2018

School should be ready for occupation by end of 2018/early 2019.

Wicklow

70821M

Coláiste Raithin, Bray

450 pupil school

Q4/2017

School ready for occupation on 31/08/2018

Wicklow

07246U

Ravenswell Primary School, Bray

24 Classroom School

Q4/2017

School ready for occupation on 18/09/2018

Wexford

63660A

Loreto Secondary School

900 pupil school

Q4/2017

School ready for occupation on 23/08/ 2018