The following table sets out the current position in relation to the schools affected by the collapse of the building contractor referred to by the Deputy.
County
|
Roll No.
|
School
|
Type of project
|
Original planned Completion date
|
Revised planned Completion date
|
Dublin City
|
20047O
|
Gaelscoil Bharra, Cabra
|
New 8 classroom school
|
07/09/2017
|
School ready for occupation on 1/9/17, some ground works still to be completed
|
Laois
|
20270R
|
Portlaoise amalgamation, (St Paul's, Sacred Heart & Scoil Mhuire) Portlaoise Rd, Portlaoise, Co. Laois.
|
New Schools - 3 existing schools amalgamating into 2 new schools -
Two new 24 classroom schools with a combined GP Hall.
|
12/04/2016
|
Jnr School ready for occupation on 9/6/17 - Snr School ready for occupation on 29/8/17, some ground works still to be completed
|
Offaly
|
72560C
|
Tullamore College
|
Demolition of the existing single storey secondary school buildings and their replacement with a 7,076m2 part single part two storey school building to provide accommodation for 675 pupils
|
29/06/2016
|
School ready for occupation on 27/2/17, some ground works still to be completed
|
Wexford
|
12372G
|
New Ross Jnr & Snr Schools, Castlemoyle
|
2 new 18 classroom schools each with a 2 classroom ASD Unit
|
15/06/2016
|
Schools ready for occupation on 25/01/17, some snags/defects still to be rectified
|
Wicklow
|
70740M
|
Arklow Community College, Coolgreaney Rd, Arklow, Co. Wicklow.
|
New school to cater for 710 pupils
|
17/06/2016
|
School ready for occupation on 23/12/15, some ground works still to be completed
|
Cork
|
71050P
|
St Colman's College, Midleton, Co Cork
|
Extension of 5,640sqm including ASD Unit PE Hall to provide accommodation for
1000 pupils
|
10/02/2017
|
School should be ready for occupation Sept 2019
|
Cork
|
70990M
|
Coláiste an Chraoibhin, Fermoy, CO Cork
|
Extension of 3,845 sqm including ASD Unit PE Hall to provide accommodation for
850 pupils
|
15/12/2016
|
School should be ready for occupation Sept 2019
|
Kildare
|
70700A
|
Maynooth Post Primary School, Maynooth
|
Replacement school for
1000 pupils
|
18/05/2019
|
School should be ready for occupation June 2020
|
Kildare
|
76193Q
|
Maynooth Community College, Maynooth
|
New 1000 pupil
with a shared Sports Hall with Maynooth Post Primary School
|
18/05/2019
|
School should be ready for occupation June 2020
|
Carlow
|
70420R
|
Tyndall College
|
1000 pupil school
|
Q1/2018
|
School should be ready for occupation by end of 2018/early 2019.
|
Carlow
|
76514K
|
Carlow Institute of Further Education
|
1000 pupil school
|
Q1/2018
|
School should be ready for occupation by end of 2018/early 2019.
|
Meath
|
64410F
|
Eureka Secondary School, Kells
|
800 pupil school
|
Q1/2018
|
School should be ready for occupation by end of 2018/early 2019.
|
Wicklow
|
70821M
|
Coláiste Raithin, Bray
|
450 pupil school
|
Q4/2017
|
School ready for occupation on 31/08/2018
|
Wicklow
|
07246U
|
Ravenswell Primary School, Bray
|
24 Classroom School
|
Q4/2017
|
School ready for occupation on 18/09/2018
|
Wexford
|
63660A
|
Loreto Secondary School
|
900 pupil school
|
Q4/2017
|
School ready for occupation on 23/08/ 2018
|