Schools Building Projects Data

Dáil Éireann Debate, Thursday - 18 October 2018

Thursday, 18 October 2018

Questions (61)

Mick Wallace

Question:

61. Deputy Mick Wallace asked the Minister for Education and Skills the number of school building projects that have been affected by building contractors running into financial difficulties since January 2018; the names of the schools in each case; and if he will make a statement on the matter. [42114/18]

View answer

Written answers

Since the beginning of 2018, 18 school building projects have been affected in respect of two contractors who have encountered financial difficulties. A list of the 18 schools in question is as follows:

County

School

Roll Number

Cork

St Colman’s College, Midleton

71050P

Cork

Coláiste an Chraoibhín, Fermoy

70990M

Kildare

Maynooth Post-Primary School

70700A

Kildare

Maynooth Community College

76193Q

Louth

Scoil Uí Mhuirí, Dunleer

71780G

Carlow

Tyndall College

70420R

Carlow

Carlow Institute of Further Education

76514K

Meath

Eureka Secondary School, Kells

64410F

Wicklow

Coláiste Ráithín, Bray

70821M

Wicklow

Ravenswell Primary School, Bray

07246U

Wexford

Loreto Secondary School

63660A

Dublin

Gaelscoil Bhaile Munna

20015B

Dublin

Gaelscoil Bharra, Cabra

20047O

Laois

Portlaoise Amalgamation

20270R & 20480F

Offaly

Tullamore College

72560C

Wicklow

Arklow Community College

70740M

Wexford

New Ross Jnr & Snr Schools

20481H & 20482J

Louth

Scoil Padraig Naofa, Drogheda

17949O

One of the building contractors in question went into Liquidation; this contractor was involved in 15 of the projects. The other contractor, who was engaged in the other three projects affected, underwent a Company Voluntary Arrangement (CVA) process, which is similar to Examinership.

Of the 18 projects - 8 of the schools are now occupied, 1 is due to be completed by late October/early November 2018, a further 4 schools are due to be completed in late 2018/2019 and 5 of the projects are currently being retendered.

On a small number of projects where the schools are occupied but some site works have yet to be completed, the Design Teams are currently in negotiation with the respective Bondsman with a view to having the works completed as soon as possible.

I would like to assure the Deputy that my Department is committed to achieving the earliest possible completion dates for all the projects concerned.