128. Deputy Barry Cowen asked the Minister for Public Expenditure and Reform the breakdown of the €687,000 capital allocation in the Office of Government Procurement for 2019, that is, Vote 39 of the budget 2019 expenditure report by specific project; the projects that will be commenced in 2019; the projects that will be completed in 2019, in tabular form; and if he will make a statement on the matter. [44468/18]

View answer

Written answers

The Office of Government Procurement has been allocated a capital budget of €687,000 for 2019. This allocation is for a mixture of project based and routine ongoing capital spend.

Below is a summary of the project based work. All projects are anticipated to be completed during 2019.

Project

2019 spend

Description

eTenders ESPD

€20,000

eESPD project completion. 

CRM

€292,000

Microsoft Dynamics365 implementation   and development.

Works on Dublin and Regional offices

€171,500

Necessary works to be carried out to   improve facilities and expand capacity

Total Project Based Spend

€483,500

 