Skip to main content
Normal View

Departmental Budgets

Dáil Éireann Debate, Thursday - 25 October 2018

Thursday, 25 October 2018

Questions (175)

Barry Cowen

Question:

175. Deputy Barry Cowen asked the Minister for Justice and Equality the breakdown of the €43,920,000 capital allocation in the justice division within his Department for 2019, that is, Vote 24 of the budget 2019 expenditure report by specific project; the projects that will be commenced in 2019; the projects that will be completed in 2019, in tabular form; and if he will make a statement on the matter. [44474/18]

View answer

Written answers

Capital funding of €43.570 million in 2019 relates to the construction of a new Forensic Science Laboratory in Backweston Co. Kildare.  While certain enabling works have already been carried out on the site it is expected that the construction of the new laboratory will commence in 2019 and is expected to be completed by 2021. The balance of the capital allocation of €0.350 million relates to ICT expenditure.

Top
Share