Dáil Éireann Debate, Tuesday - 12 February 2019

Tuesday, 12 February 2019

Questions (573)

Timmy Dooley

Question:

573. Deputy Timmy Dooley asked the Minister for Communications, Climate Action and Environment if a matter regarding the case of a person (details supplied) will be addressed. [6325/19]

View answer

Written answers

In April 2017 my Department published an updated version of the National Broadband Plan (NBP) High Speed Broadband Map. This is available at www.broadband.gov.ie. The map shows the areas targeted by commercial operators to provide high speed broadband services and the areas that will be included in the State Intervention Area under the National Broadband Plan. The Map is colour coded and searchable by address/Eircode:

· The AMBER area represents the parts of the country where commercial operators have no plans to build high speed broadband networks. Premises in the AMBER area will be provided with high Speed Broadband through a State Intervention.

· The BLUE area represents those areas where commercial providers are either currently delivering or have plans to deliver high speed broadband services.

· The LIGHT BLUE area represents eir's commercial rural deployment plans to rollout high speed broadband to 300,000 premises as part of a Commitment Agreement signed with my Department in April 2017.

The table below details the percentage of premises to be covered by the State Intervention and through commercial investment in the Ballymorris area.

Townland

Premises within the NBP Intervention Area

Premises within Commercial Operator’s Area

Premises within eir planned rural deployment

Ballymorris

25% (33)

74% (99)

1% (1)

Information on categories of specific premises can be accessed on my Department’s website, www.broadband.gov.ie, by entering the relevant Eircode.

The procurement process to appoint a bidder for the State intervention network is now at the final stage. My priority is to bring the procurement process to a fair and impartial conclusion as quickly as possible and I will bring a recommendation to Government in the coming weeks.

Under a Commitment Agreement signed with my Department in April 2017, eir is in the process of passing 300,000 predominantly rural homes with high speed broadband. According to data for Q3 2018 submitted by eir to my Department the company has passed almost 210,000 premises nationwide as part of its ongoing deployment.

Information on eir's rural deployment is available on that company’s website, http://fibrerollout.ie/Eircode-lookup/. A copy of the Commitment Agreement is available on my Department’s website, www.dccae.gov.ie.

For those premises currently awaiting access to high speed broadband, practical initiatives will continue to be addressed through the work of the Mobile Phone and Broadband Taskforce to address obstacles and improve connectivity in respect of existing and future mobile phone and broadband services.

Under this Taskforce, engagement between telecommunications operators and local authorities through the Broadband Officers is continuing. These Broadband Officers are acting as single points of contact in local authorities for their communities. The appointment of these officers is already reaping rewards in terms of ensuring a much greater degree of consistency in engagements.