Capital Expenditure Programme

Dáil Éireann Debate, Thursday - 14 February 2019

Thursday, 14 February 2019

Questions (105)

Jonathan O'Brien

Question:

105. Deputy Jonathan O'Brien asked the Minister for Education and Skills the capital projects completed by his Department since 2011; the initial contract value of same; the final cost of same; and the final cost of the capital projects that have had an ex post review in tabular form. [7848/19]

View answer

Written answers

School building projects in excess of €10m typically arise at post-primary level rather than at primary level.

Building Contracts in excess of €10m

Numbers

County

Roll No.

School

Year

Contract Sum Incl VAT

Date LOA signed/

Contract commenced

Final Account Agreed Sum incl VAT

Reason for variation: Change Orders, Conciliation etc

1

Cork

68264R

Edmund Rice College, Carrigaline

2017

€13,322,007.84

24/03/2016

€14,683,207.60

Approved change orders

2

Dublin

60029J

Clonkeen College, Dublin

2017

11,303,020

22/06/2015

11,615,716.32

Approved Change Order

3

Limerick

20175A

Limerick ETNS (Linked with 20181S)

2017

€12,451,133.76

30/08/2016

€12,668,568.52

Approved change orders

Limerick

20181S

GS an Raithin (Linked with 20175A)

2017

4

Dublin

68082L

Coláiste Ghlór na Mara, Balbriggan

2016

€14,364,344.28

06/11/2015

14,911,274.40

Approved change orders

5

Meath

76196W

Ashbourne Post-Primary School, Ashbourne - linked to 20382F and 20396Q

2016

€17,308,750.00

10/09/2015

€18,303,847.37

Approved change orders

Meath

20382F

Gaelscoil Na Mí, Ashbourne - linked to 76196W & 20396QO

2016

Meath

20396Q

Ashbourne Educate Together National School, linked to 76196W & 20382F

2016

6

Cork

62640M

St Angela's College, Cork

2015

11,423,467.50

10/03/2014

13,039,322.04

Approved Change Order and Conciliation Award

7

Dublin

76129H

Ardgillan Community College, Balbriggan

2015

12,319,627.51

01/07/2013

13,194,070.88

Approved Change Orders

8

Dublin

76152C

Clonburris Post-Primary School, Clonburris, Lucan

2015

€12,892,172.11

27/03/2014

€15,761,147.55

Approved change orders and conciliation

9

Galway

71330V

Coláiste na Coiribe, Bóthar Thuama

2015

€10,830,109.00

21/7/2014

€11,524,790

Approved change orders

10

Dublin

81001L

Newpark Comp, Blackrock

2014

12,468,451.03

09/07/2013

12,733,512.97

Approved Change orders

11

Meath

76173K

Coláiste na Mí, Navan (linked to 20179I)

2014

€11,379,235.42

20/12/2012

11,668,067.63

Approved change orders

Meath

20179I

St Stephen's NS, Navan (linked to 76173K)

2014

12

Meath

18762D

SN Realt na Mara (Girls) Mornington (joint project with 18767M)

2014

€10,101,818.49

04/01/2013

€10,354,045

Approved change orders

Meath

18767M

SN Realt na Mara (Boys) Mornington (joint project with 18762D)

2014

13

Dublin

76130P

Luttrellstown Community College

2013

€13,046,425.00

01/08/2012

€13,369,738.02

Approved change orders

14

Monaghan

76091I

Gaelcholáiste Oiriall (Linked to 76095Q & 19936P)

2013

€30,770,156.53

15/08/2011

€31,643,045.78

Approved change orders

Monaghan

76095Q

Monaghan Institute of Further Education (Linked to 76091I & 19936P

2013

Monaghan

19936P

Gaelscoil Ultain (Linked to 76095Q & 76091I)

2013

15

Dublin

76098W

Pobail Scoil Setanta, Phibblestown - linked to 20247W

2011

€19,921,240.77

16/12/2008

€20,292,897.58

Approved change orders

Dublin

20247W

Scoil Grainne, Phibblestown - linked to 76098W

2011

It can generally take quite a while for final accounts on projects to be submitted by contractors and then get finalised and agreed. The attached table sets out the position in respect of large-scale school building projects in excess of €10m where the final account has been agreed. In summary, it shows that there was just over a 5% difference between the tender (contract) sum and the agreed final account for large-scale school building projects delivered since 2011. There is a process in place for dealing with requests for change orders to existing contracts and these typically relate to matters such as unforeseen events during the construction process, requirement for additional works etc.

My Department carefully manages and control costs on all projects in order to ensure best possible outcomes for the investment being made under the capital programme.

The measures in place to manage and control costs on large-scale school building projects include:

- Detailed procedures in place for appraisal, design, tender and construction of large-scale school building projects.

- Standardisation of sizes and layouts for classrooms and other rooms in schools.

- Detailed design team procedures that involve Department approval for progression through the various stages of design and tendering.

- NDesign Team fees tendered on percentage basis and then locked in to a fixed sum when design has been developed at Stage 2A of design process.

- Planning permission and design completed before tender process commences which gives clarity to tenderers on scope of project

- Contracts tendered on a fixed price basis using the standard form of Government contract – which gives certainty in relation to managing the impact of construction inflation.

- Procedures in place for provision of monthly progress reports and arrangements for dealing with any requests for change orders to existing contracts.

In addition to the school projects listed in the attachment 20 schools were delivered during the period by way of Public Private Partnership (PPP). In the case of such projects, the cost (which also includes Facilities Management and lifecycle costs) is determined at Financial Close and payment by the Department is by way of monthly Unitary Charges over the operational period, usually 25 years.

Information in respect of capital projects in the Higher Education Sector with building contracts in excess of €10m and with final accounts agreed will be forwarded separately to the Deputy when the relevant information is collated and finalised.