I am very aware of the school building project to which the Deputy refers. The ongoing delay of this project is extremely disappointing and frustrating for all parties involved.
The Deputy will be aware that the project had been scheduled for completion for September 2018. However, the contractor experienced a number of issues such as unforeseen ground conditions and the severe weather events of early 2018. The expected completion date for the project is now July 2019.
The project is being delivered by Westmeath County Council (WCC) which is continuing to pursue the contractor for as speedy a delivery of the project as possible. The Council has the full support of my Department in its efforts to achieve this without compromising the integrity of the building being delivered.
To ensure that the school is kept fully up to date with progress on the project, WCC is issuing monthly progress reports to the school's Board of Management. This approach will provide accurate and precise information to help the school to plan and manage its needs until its permanent accommodation is available. The Deputy may also wish to note that officials from Department recently joined WCC at a meeting with the school authority so as to discuss and address their concerns.