National Broadband Plan Implementation

Dáil Éireann Debate, Tuesday - 26 March 2019

Tuesday, 26 March 2019

Questions (1026)

Niamh Smyth

Question:

1026. Deputy Niamh Smyth asked the Minister for Communications, Climate Action and Environment the position regarding a matter in relation to broadband (details supplied). [12981/19]

View answer

Written answers

In April 2017 my Department published an updated version of the National Broadband Plan (NBP) High Speed Broadband Map. This is available at www.broadband.gov.ie. The map shows the areas targeted by commercial operators to provide high speed broadband services and the areas that will be included in the State Intervention Area under the National Broadband Plan. The Map is colour coded and searchable by address/Eircode:

- The AMBER area represents the parts of the country where commercial operators have no plans to build high speed broadband networks. Premises in the AMBER area will be provided with high Speed Broadband through a State Intervention.

- The BLUE area represents those areas where commercial providers are either currently delivering or have plans to deliver high speed broadband services.

- The LIGHT BLUE area represents eir's commercial rural deployment plans to rollout high speed broadband to 300,000 premises as part of a Commitment Agreement signed with my Department in April 2017.

There are 37 premises in the townland of Knockatallon, Co. Monaghan. 26 (70%) fall within the AMBER area and will be served under the State led Intervention, while 11 (30%) of premises are in a BLUE area and are or will be served by commercial providers.

The correspondence forwarded by the Deputy makes reference to the commercial deployment of high speed broadband in the Knockatallon area. This deployment is part of eir's commercial roll out of high speed broadband to 300,000 predominantly rural premises, in line with a Commitment Agreement signed with my Department in April 2017.

eir’s rural investment in high speed broadband is an entirely commercial undertaking, and not part of the planned State Intervention network. Although the deployment is monitored under the terms of the Commitment Agreement, it is not funded by the State and it is not planned, designed or directed by my Department in any capacity.

Decisions made by private telecommunication operators relating to the roll out and siting of infrastructure to provide high speed broadband services throughout Ireland are undertaken on a commercial basis. I have no statutory role or function in such commercial decisions of private operators, and therefore cannot direct operators regarding infrastructure installation or delivery of services.

The procurement process to appoint a bidder for the State intervention network is now at the final stage. I will bring a recommendation to Government in relation to the NBP in the coming weeks.

For those premises currently awaiting access to high speed broadband, practical initiatives will continue to be addressed through the work of the Mobile Phone and Broadband Taskforce to address obstacles and improve connectivity in respect of existing and future mobile phone and broadband services.

Under this Taskforce, engagement between telecommunications operators and local authorities through the Broadband Officers is continuing. These Broadband Officers are acting as single points of contact in local authorities for their communities. The appointment of these officers is already reaping rewards in terms of ensuring a much greater degree of consistency in engagements.