Dáil Éireann Debate, Thursday - 16 May 2019

Thursday, 16 May 2019

Questions (149)

Clare Daly

Question:

149. Deputy Clare Daly asked the Minister for Communications, Climate Action and Environment the status of the roll-out of broadband in an area (details supplied); and the steps being made to address gaps in coverage in the area. [21245/19]

View answer

Written answers

In April 2017, my Department published an updated version of the National Broadband Plan (NBP) High Speed Broadband Map. This is available at www.broadband.gov.ie.

The map shows the areas targeted by commercial operators to provide high speed broadband services and the areas that will be included in the State Intervention Area under the National Broadband Plan. The Map is colour coded and searchable by address/Eircode:

- The AMBER area represents the parts of the country where commercial operators have no plans to build high speed broadband networks. Premises in the AMBER area will be provided with high Speed Broadband through a State Intervention.

- The BLUE area represents those areas where commercial providers are either currently delivering or have plans to deliver high speed broadband services.

- The LIGHT BLUE area represents eir's commercial rural deployment plans to rollout high speed broadband to 300,000 premises as part of a Commitment Agreement signed with my Department in April 2017.

The table below details the percentage of premises to be covered by the State Intervention and through commercial investment in the areas identified by the Deputy. eir's deployment within the townlands of Magillstown and Balheary is now complete.

Townland

Premises within the NBP Intervention Area

Premises within Commercial Operator’s Area

Premises within eir planned rural deployment

Total

Magillstown

59% (13)

41% (9)

0% (0)

100% (22)

Balheary

45% (17)

55% (21)

0% (0)

100% (38)

Premises where commercial providers are not currently delivering or have indicated no plans to deliver high speed broadband services will be addressed through the National Broadband Plan State led Intervention.

This intervention is the subject of the procurement process to engage a company to build, operate and maintain the NBP State intervention network. Following rigorous evaluation by my Department, I recently brought a recommendation to Government to confer Preferred Bidder status on Granahan McCourt, the remaining bidder in the NBP procurement process and Government has agreed to this at its meeting on 7 May.

The Government Decision of 7 May 2019 means that it is intended to award the State Intervention contract to the Bidder. This award is subject to contract close including finalisation of financial and legal documents. Deployment of the NBP State Intervention network will commence shortly after that.

The Bidder has indicated that the NBP State intervention will take an estimated 7 years from the beginning of deployment.

In the first year of this roll out, the Bidder will deploy approximately 300 Broadband Connection Points (BCPs) across all counties. It is anticipated that between 7 and 23 BCPs will be deployed in each county. BCPs will provide a community based high speed broadband service, enhancing online participation and allowing for the establishment of digital work hubs in these locations. A deployment plan will be made available by the bidder once the contract is signed. The Bidder is aiming to pass 133,000 premises by end of the second year of the overall deployment, with 70-100,000 passed each year thereafter until roll out is completed.