Broadband Service Provision

Dáil Éireann Debate, Tuesday - 28 May 2019

Tuesday, 28 May 2019

Questions (365)

Timmy Dooley

Question:

365. Deputy Timmy Dooley asked the Minister for Communications, Climate Action and Environment if broadband will be reviewed for a location (details supplied); and if he will make a statement on the matter. [22497/19]

View answer

Written answers

The National Broadband Plan aims to ensure that every home, school and business in Ireland has access to high speed broadband. This is being achieved through a combination of commercial investment across the country, and a State intervention in those areas where commercial operators acting alone are unlikely to invest.

The NBP has been a catalyst in encouraging investment by the telecoms sector. In 2012, less than 700,000, or 30% of Irish premises had access to high speed broadband. Today, 74% of the 2.4 million premises in Ireland can access high speed broadband.

The premises referenced by the Deputy is in the AMBER area on the National Broadband Plan (NBP) High Speed Broadband Map, which is available on my Department's website at www.broadband.gov.ie. The AMBER areas represent the target areas for the proposed State led Intervention under the NBP.

This intervention is the subject of the procurement process to engage a company to build, operate and maintain the NBP State intervention network. Following rigorous evaluation by my Department, I recently brought a recommendation to Government to confer Preferred Bidder status on Granahan McCourt, the remaining bidder in the NBP procurement process and Government agreed to this at its meeting on 7 May.

The Government Decision means that it is intended to award the State Intervention contract to the Bidder. This award is subject to contract close including finalisation of financial and legal documents. Deployment of the NBP State Intervention network will commence shortly after that. The Bidder has indicated that the NBP State intervention will take an estimated 7 years from the beginning of deployment.

In the first year of this roll-out, the Bidder will deploy approximately 300 Broadband Connection Points (BCPs) across all counties. It is anticipated that between 7 and 23 BCPs will be deployed in each county. BCPs will provide a community based high speed broadband service, enhancing online participation and allowing for the establishment of digital work hubs in these locations.

A deployment plan will be made available by the Bidder once the contract is signed. The Bidder is aiming to pass 133,000 premises at the end of the second year, with 70-100,000 passed each year thereafter until roll-out is completed.

Question No. 366 answered with Question No. 364.