Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 11 June 2019

Tuesday, 11 June 2019

Questions (239)

Mary Butler

Question:

239. Deputy Mary Butler asked the Minister for Education and Skills the status of an application by a school (details supplied) since revised stage 2 drawings and details were submitted in February 2019; and if he will make a statement on the matter. [23480/19]

View answer

Written answers

In April 2018, my Department approved funding for the provision of one additional classroom and one Special Education Teaching room together with a WC for assisted users at the school to which the Deputy refers.

A Stage 2a submission (detailed design) for this project was received in my Department in February, 2019. This was assessed at that time and, following on from this, revised plans and costings were requested for submission by the school authority and its Design Team.

This revised submission, dated April 2019, was received in my Department in May 2019 and is currently being assessed.

When this assessment is completed, my Department will be in contact with the school authority directly.