Hospitals Capital Programme

Dáil Éireann Debate, Thursday - 19 September 2019

Thursday, 19 September 2019

Questions (147)

Barry Cowen

Question:

147. Deputy Barry Cowen asked the Minister for Health if the Sligo central sterile services department has commenced; if so, the stage the project is at; when the project is expected to go out for tender; when construction will commence; when the project will be completed; the estimated cost of the project; the amount spent to date; and if he will make a statement on the matter. [38062/19]

View answer

Written answers

The Health Service Executive recently published its Capital Plan for 2019-2021 outlining 250 projects to be progressed over the three-year period.

The Capital Plan includes the new central sterile services department (CSSD) at Sligo University Hospital, which is currently at design stage.

It is important to recognise that all capital development proposals must progress through a number of approval stages, in line with the Public Spending Code, including detailed appraisal, planning, design and procurement, before a firm timeline or funding requirement can be established. 

The delivery of capital projects is a dynamic process and is subject to the successful completion of the various approval stages, which can impact on the timeline for delivery.

The HSE actively manages the capital programme in order to ensure it has flexibility to progress as many projects as possible within the available funding, particularly in the event of any project not progressing as anticipated.

As the Health Service Executive is responsible for the delivery of public healthcare infrastructure projects, I have asked the HSE to respond to you directly in relation to this matter.