Broadband Service Provision

Dáil Éireann Debate, Tuesday - 1 October 2019

Tuesday, 1 October 2019

Questions (465)

Fiona O'Loughlin

Question:

465. Deputy Fiona O'Loughlin asked the Minister for Communications, Climate Action and Environment when broadband will be available in an area (details supplied); and if he will make a statement on the matter. [39509/19]

View answer

Written answers

Every home, farm, school and business in Ireland will have access to high speed broadband – no matter where they are located – following the Government’s decision to approve the appointment of a Preferred Bidder to the National Broadband Plan. Under this plan, Ireland will become one of the first countries in the world to ensure that those in rural areas have the same digital opportunities as those in urban areas. The premises referenced by the Deputy is located in the AMBER area on the National Broadband Plan (NBP) High Speed Broadband Map, which is available on my Department's website at www.broadband.gov.ie. The AMBER areas represent the target areas for the proposed State led Intervention under the NBP.

The Deputy also referred to the premises' proximity to a commercial deployment of high speed broadband. This deployment is part of eir's commercial roll out of high speed broadband to 300,000 predominantly rural premises, in line with a Commitment Agreement signed with my Department in April 2017.

eir’s rural investment in high speed broadband is an entirely commercial undertaking, and not part of the planned State Intervention network. Although the deployment is monitored under the terms of the Commitment Agreement, it is not funded by the State and it is not planned, designed or directed by my Department in any capacity.

Decisions made by private telecommunication operators relating to the roll out and siting of infrastructure to provide high speed broadband services throughout Ireland are undertaken on a commercial basis. I have no statutory role or function in such commercial decisions of private operators, and therefore cannot direct operators regarding infrastructure installation or delivery of services.

The State intervention is the subject of the procurement process to engage a company to build, operate and maintain the NBP State intervention network. In May I brought a recommendation to Government to confer Preferred Bidder status on Granahan McCourt, the remaining bidder in the NBP procurement process and Government agreed to this.

The Government Decision of 7 May 2019 means that it is intended to award the State Intervention contract to the Bidder. This award is subject to contract close. The finalisation of financial closure and legal requirements are progressing towards contract award. Deployment of the NBP State Intervention network will commence shortly after that.

The Bidder has indicated that the NBP State intervention will take an estimated 7 years from the beginning of deployment.

A deployment plan will be made available by the Bidder once the contract is signed. In the first year of roll out, the Bidder will deploy approximately 300 Broadband Connection Points (BCPs) across all counties. It is anticipated that between 7 and 23 BCPs will be deployed in each county. BCPs will provide a community based high speed broadband service, enhancing online participation and allowing for the establishment of digital work hubs in these locations.

The Bidder is aiming to pass 133,000 premises at the end of the second year, with 70-100,000 passed each year thereafter until roll out is completed.

Work continues on finalising the contract and in parallel to this work, I am considering the recommendations of the Joint Oireachtas Communications Committee report which was published recently. I will bring my deliberations of the report to Government in due course.