Skip to main content
Normal View

Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 26 November 2019

Tuesday, 26 November 2019

Questions (229)

Dara Calleary

Question:

229. Deputy Dara Calleary asked the Minister for Education and Skills the status of a school building project (details supplied) in County Mayo; and if he will make a statement on the matter. [49135/19]

View answer

Written answers

A major school building project to provide new accommodation for the school referred to by the Deputy has recently been authorized to proceed to tender for the appointment of a Main Contractor and Reserved Specialists. The closing date for receipt of the completed tender for the Main Contractor is the end of December 2019.

Subject to no issues arising during the tender process, it is anticipated that the project will progress to site by early third quarter of 2020 with a construction period of approximately 24 months.

Top
Share