European Court of Justice Rulings

Dáil Éireann Debate, Tuesday - 26 November 2019

Tuesday, 26 November 2019

Questions (512)

Seán Haughey

Question:

512. Deputy Seán Haughey asked the Minister for Housing, Planning and Local Government the way in which he plans to respond to the imposition of a €5 million fine on Ireland by the European Court of Justice in respect of a wind farm in County Galway; and if he will make a statement on the matter. [48795/19]

View answer

Written answers

In the judgment delivered on 12 November 2019, the Court of Justice of the European Union in case C-261/18 (the Derrybrien Wind farm case) ruled against Ireland and imposed the lump sum fine of €5m referred to in the question.

While detailed payment instructions are awaited from the EU Commission, the lump sum fine of €5m will likely be payable before end 2019. It is understood the Commission will be in contact with Ireland over the coming weeks regarding the payment procedures involved for the lump sum fine and the separate daily fines.

Top
Share