Question:

153. Deputy Brendan Howlin asked the Minister for Education and Skills further to Parliamentary Question No. 153 of 12 November 2019, the number of tenders received for the building project by the closing date of the end of November 2019; the estimated time it will take to review the tenders and award a contract; and if he will make a statement on the matter. [52101/19]

View answer

Written answers

The project to which the Deputy refers is currently at tender stage. The closing date for tenders has now passed and six tenders have been returned. The Department expects that the Tender Report will be submitted by the Design Team in the coming weeks.

Subject to no issues arising, it is anticipated that construction will commence in the 1st quarter of 2020 and the project is expected to take approximately 20 months to complete.