The following spreadsheet details the 13 projects that have progressed from an advanced stage of architectural planning - Stage 2(b), Detailed Design to the next stage of architectural planning - Stage 3, Tender Stage since the start of the 2019/20 academic year.
Thereafter, a tender stage normally takes between 7 and 8 months to complete depending on the size and complexity of the project.
Major Projects progressed to Stage 3 (Tender) since 1st September 2019
|
Project Type & Delivery
|
County
|
Roll No
|
School
|
Date progress to Stage 3 (Tender Stage)
|
|
|
|
|
|
Major Projects - TRAD
|
Donegal
|
19313C
|
Glenswilly NS
|
06/09/2019
|
|
|
|
|
|
|
|
|
|
|
|
Donegal
|
18625Q
|
Scoil Cholmcille, Letterkenny
|
27/09/2019
|
|
|
|
|
|
|
|
|
|
|
|
Donegal
|
19927O
|
St. Mary's, Stranorlar
|
27/09/2019
|
|
|
|
|
|
|
|
|
|
|
|
Mayo
|
64520M
|
St. Mary's, Ballina
|
01/10/2019
|
|
|
|
|
|
|
|
|
|
|
|
Kildare
|
16706G
|
St. Joseph's, Kilcock
|
26/09/2019
|
|
|
|
|
|
|
|
|
|
|
|
Kildare
|
61702D
|
St. Paul's Monasterevin
|
26/09/2019
|
|
|
|
|
|
|
|
|
|
|
|
Wicklow
|
61830M
|
St. David's, Greystones
|
11/12/2019
|
|
|
|
|
|
|
|
|
|
|
Major Projects - ADAPT
|
Cork
|
6209D
|
Scoil Mhuire Gan Smál, Blarney
|
18/11/2019
|
|
|
|
|
|
|
|
|
|
|
|
Kildare
|
17872F & 17873H
|
St. Conleth & St. Mary's, Newbridge
|
18/10/2019
|
|
|
|
|
|
|
|
|
|
|
|
Tipperary
|
18716T
|
Cahir
|
12/12/2019
|
|
|
|
|
|
|
|
|
|
|
|
Dublin
|
20176C
|
Rush & Lusk
|
04/11/2019
|
|
|
|
|
|
|
|
|
|
|
Major Projects - Devolved
|
Cork
|
14052V
|
Kanturk BNS (S-B) (with RN 17087J)
|
07/11/2019
|
|
|
|
|
|
|
|
|
|
|
|
Dublin
|
20131D
|
Dublin 7 ETNS
|
End Aug/Early Sep 2019
|
|
|
|
|
|