National Broadband Plan Implementation

Dáil Éireann Debate, Tuesday - 17 December 2019

Tuesday, 17 December 2019

Questions (562)

Pádraig O'Sullivan

Question:

562. Deputy Pádraig O'Sullivan asked the Minister for Communications, Climate Action and Environment the progress since 2011 to provide broadband to a location (details supplied) in County Cork; and if he will make a statement on the matter. [52976/19]

View answer

Written answers

The National Broadband Plan (NBP) is the Government’s plan to rollout high speed broadband to the 1.1 million people living and working in the nearly 540,000 premises including almost 100,000 businesses and farms, along with 695 schools where commercial operators will not commit to deliver the service.

The Question relates to premises which are located in the AMBER area on the NBP High Speed Broadband Map, which is available on my Department's website at www.broadband.gov.ie. The AMBER area represents the area to be served by the network to be deployed under the NBP State led Intervention, the contract for which was signed on 19 November with National Broadband Ireland (NBI).

These premises were originally in the BLUE area, meaning commercial operators had planned to provide high speed broadband to the area. As commercial operators’ plans to serve these premises have not materialised, these premises have now been included in the Intervention area for the NBP following the recent NBP Mapping Consultation. This is why the premises are AMBER dots in a BLUE area

Work has already begun and a deployment plan will be made available by NBI shortly. All counties will see premises passed in the first 2 years and over 90% of premises in the State will have access to high speed broadband within the next four years.

Approximately 300 Broadband Connections Points (BCPs), including schools, library hubs and local sports halls in every county in Ireland, will be connected to high speed broadband during 2020, to enable communities to quickly get free public access to high speed broadband. The BCP locations are available to view on the High Speed Broadband Map on the Department’s website www.dccae.gov.ie.

The BCPs have been specifically selected by the local authorities so that they can provide public Wi-Fi and other facilities to support mini digital/enterprise hubs to the local community in advance of the main NBP deployment. Broadband Officers in each Local Authority were tasked with consulting with local communities and business to find the appropriate mix of locations to reap the maximum benefits.

By the end of 2021, NBI plans to pass approximately 115,000 premises, with 70,000 - 100,000 passed each year thereafter until rollout is completed. NBI has indicated that the network rollout will take an estimated 7 years from the beginning of deployment.