Schools Building Projects Status

Dáil Éireann Debate, Thursday - 5 March 2020

Thursday, 5 March 2020

Questions (228)

Darragh O'Brien

Question:

228. Deputy Darragh O'Brien asked the Minister for Education and Skills the status of the refurbishment and provision of an extension for a school (details supplied); and if he will make a statement on the matter. [3028/20]

View answer

Written answers

The building project for the school referred to by the Deputy is included in my Department’s Construction Programme which is being delivered under the National Development Plan.

This project is one of the school building projects on my Department’s ADAPT 2 (Accelerated Delivery of Architectural Planning & Tendering) Programme. My Department has completed the process of appointing a Project Manager for the ADAPT 2 Programme, which currently contains 18 school building projects.

The appointment of a Design Team (Architect, Quantity Surveyor, Civil & Structural Engineer, Mechanical & Electrical Engineer and Project Supervisor for the Design Process) for the school in question has been completed. 

The Department held a briefing session along with the Project Manager, the School and Design Team on January 15th 2020. The Design Team is currently working on Stage 1 of Architectural Planning which includes Site Report, Site Suitability and producing Initial Sketch Schemes.