226. Deputy Darren O'Rourke asked the Minister for Public Expenditure and Reform the Garda stations within the Meath division that are being refurbished by the OPW; the Garda stations within the division that are due to be refurbished by the OPW over the next 12 months; the status of each project; and when each refurbishment project is due to be completed. [14001/20]

View answer

Written answers

I can confirm that the Office of Public Works (OPW) is currently carrying out cell refurbishment works at Kells Garda Station. These works are due for completion in September 2020.

A new two story extension to include 4 new cells, prisoner processing facilities with ancillary rooms and new office accommodation is planned for Navan Garda Station. Tender documents will be issued shortly and works are expected to commence in late 2020 and completed in 2021.

In addition to these projects the OPW continues to provide ongoing maintenance to all the Garda stations in the Meath Division as required.