Dáil Éireann Debate, Tuesday - 28 July 2020

Tuesday, 28 July 2020

Questions (277)

Catherine Murphy

Question:

277. Deputy Catherine Murphy asked the Minister for Public Expenditure and Reform if the development of the Leeson Lane office building project has commenced; when the project will be completed; and the estimated cost of the project. [18460/20]

View answer

Written answers

The tender documentation for the development of the Leeson Lane Office Building Project is complete and is awaiting approval from the Sponsoring and Sanctioning Authority to issue tender documentation to prequalified contractors as required by the Public Spending Code and the Capital Works Management Framework. The tender issue process and assessment takes approximately four to six months. The construction period is two years. OPW do not normally disclose the cost of the project prior to tender for commercially sensitive reasons.