473. Deputy Catherine Murphy asked the Minister for Education the amount due to be spent on major refurbishment works being carried out at both Naas and Maynooth community colleges; and when works will be completed on both colleges. [26824/20]

View answer

Written answers

The Deputy will be aware that new building projects for the schools to which she refers have been devolved for delivery to Kildare and Wicklow Education and Training Board (KWETB)

It is expected that the Naas Community College building will be completed in August 2021 at a total cost of approximately €25 million including the provision of temporary accommodation.

I am pleased to inform the Deputy that the Maynooth Community College building has achieved partial handover today and elements of the building are available for use in that context. It is anticipated that the remaining elements of the main school building will be completed towards the end of the year. The project is expected to be fully completed in February 2021 once the PE facility shared with Maynooth Post-Primary School is available for occupation.

As Maynooth Community College is being delivered as part of a campus development with Maynooth Post Primary School, including the shared PE facility, it is not possible to separate out costs specific to Maynooth Community College. However, I can inform the Deputy that it is anticipated that the total cost of delivering this campus project including expenditure on previous contracts will be approximately €51 million.