Capital Expenditure Programme

Dáil Éireann Debate, Tuesday - 3 November 2020

Tuesday, 3 November 2020

Questions (1570)

Matt Shanahan

Question:

1570. Deputy Matt Shanahan asked the Minister for Agriculture, Food and the Marine if he will provide all disbursements of capital spending above €20 million on completed projects for each year since 2016 by name of project, department or body responsible for delivering project, county, NUTS3 region, type of investment, construction commencement, completion year and actual cost in tabular form. [34184/20]

View answer

Written answers

My Department has completed one capital project over €20m since 2016.

In 2019, the project for the remediation of the East Tip, Haulbowline Island, Co. Cork under NUTS 3 Region Cork/South West IE053 was completed. My Department assumed responsibility for remediation works at Haulbowline Island in 2012.

In the period up to 2017, expenditure was focussed on preparing for and securing the necessary planning and waste licence consents, and upgrading the island infrastructure in anticipation of works. Construction work on the East Tip site commenced in October 2017 and remediation works are complete with the project now in a maintenance phase.

The total expenditure incurred by my Department (including expenditure commissioned by Cork County Council acting as my agents for the project and reimbursed through the Department) to the end of 2019 is €25,034,676.