Dáil Éireann Debate, Wednesday - 9 December 2020

Wednesday, 9 December 2020

Questions (115)

Kathleen Funchion

Question:

115. Deputy Kathleen Funchion asked the Minister for Education if a school (details supplied) will be included in the next tender bundle for its building project; if the required documentation is being prepared; and if she will make a statement on the matter. [42273/20]

View answer

Written answers

I wish to advise the Deputy that a tender process is ongoing for the establishment of a new framework of contractors for delivery of a bundle of design and build projects which is expected to be completed in Quarter 1 of 2021. This school building project will be included in a subsequent bundle of projects, to be tendered to the new framework when established, which is expected to be Quarter 2 of 2021.  Tender documents are currently in preparation.