317. Deputy Brendan Smith asked the Minister for Public Expenditure and Reform the expected timeline for each stage in the provision of new public service accommodation (details supplied); and if he will make a statement on the matter. [44424/20]

View answer

Written answers

Tender documentation for the Main, Mechanical and Electrical elements of the Project in question has issued to the pre-qualified firms. It is expected that the procurement phase of the process will be completed in quarter 2 2021. Following Contract Award construction will take about 20 months to complete.